How to Get a Fence Permit in Spokane, WA (2026 Guide)

Everything you need to know about fence permits in Spokane, WA, local requirements, fees, timelines, and how to apply.

By Joey, Founder · Last updated May 15, 2026 · How we research →

$50 – $200 Permit Fees
about 2 weeks Approval Time
3 Local Rules

Check your specific fence project

Get an instant, personalized answer for your exact project details in Spokane.

Free Permit Lookup →

Do You Need a Fence Permit in Spokane?

Based on Spokane's local building codes, you'll need a permit when:

Required·Rule 1

Fences over 6 feet require a building permit.

SourceCity of Spokane Code / WA State Building Code / 2021 IRC

These fence projects are typically exempt in Spokane:

Exempt·Rule 1

Backyard fences 6 feet or under typically do not require a building permit.

SourceCity of Spokane Code / WA State Building Code / 2021 IRC
Exempt·Rule 2

Front yard fences 4 feet or under typically do not require a permit but must comply with zoning.

SourceCity of Spokane Code / WA State Building Code / 2021 IRC

Permit Fees in Spokane

Based on local Spokane permit data, fees for fence projects typically range:

$50 – $200 Spokane Permit Fee Range

Here's how fees break down by project scope nationally:

Project ScopeTypical Permit Fee
Simple residential fence (under 6 ft)$25 – $150
Front-yard or taller fence (6+ ft)$50 – $200
Masonry or engineered fence$150 – $500+
Pool barrier fence$50 – $200
Inspection fee (if separate from permit)$25 – $85
Structural engineering (masonry walls, if required)$500 – $2,000+ (separate from permit)

Fees are typically calculated based on estimated project value. Contact Development Services Center for exact amounts.

How Long Does It Take?

In Spokane, typical approval time for fence permits is about 2 weeks.

More complex projects requiring structural review or variances may take longer. Simple projects may qualify for expedited or over-the-counter review in some cases.

How to Apply for a Fence Permit in Spokane

  1. 1 Check requirements: Use our free lookup tool or contact Development Services Center to confirm your project needs a permit.
  2. 2 Gather documents: Prepare your application, site plan, construction drawings, and any other required documents.
  3. 3 Submit online: Spokane accepts applications online at Development Services Center.
  4. 4 Pay fees: Pay the applicable permit fees ($50 – $200).
  5. 5 Wait for approval: Your application will be reviewed by Spokane plan reviewers. Typical turnaround is about 2 weeks.
  6. 6 Begin work: Once approved, post your permit visibly at the job site before starting work.
  7. 7 Schedule inspections: Call Development Services Center at (509) 625-6300 to schedule required inspections at each phase of the project.

Spokane Building Department Contact

NameDevelopment Services Center
Apply OnlineApply online
Address808 W Spokane Falls Blvd, 3rd Floor, Spokane, WA 99201
HoursMon/Tue/Thu/Fri 8am-5pm; Wed 11am-5pm

Required Inspections in Spokane

Most fence projects in Spokane require inspections at each construction stage:

Inspection·Stage 1

Post Hole / Footing Inspection, Hole depth (typically 1/3 to 1/2 of the above-ground post height, and below the frost line in cold climates), hole diameter (typically 3x the post width), bearing on undisturbed soil, correct post locations matching the approved site plan, and proper setback from property lines and easements.

WhenAfter holes are dug but before concrete is poured or backfill is placed, this is the most common fence inspection
Common FailuresHoles not deep enough, posts placed within an easement, fence location doesn't match the approved site plan, holes not below the frost line.
Inspection·Stage 2

Final Inspection, Overall height compliance with the approved plans, correct location and setbacks, structural integrity, proper gate operation, material compliance, 'good side out' compliance (if applicable), and general code compliance. For pool barrier fences: self-closing gates, self-latching mechanism at 54 inches, no climbable features, and no openings larger than 4 inches.

WhenAfter the fence is fully installed, posts, rails, pickets/panels, and gates
Common FailuresFence exceeds approved height, gate doesn't self-close properly (pool fences), fence not matching the approved location, 'good side' facing inward instead of outward.

Schedule inspections with Development Services Center at (509) 625-6300 at least 24–48 hours in advance.

Frequently Asked Questions

Whether you need a permit depends on the size and scope of your fence project. In Spokane, some smaller projects are exempt while larger ones require a permit. Use our free lookup tool to check your specific situation.

Permit fees for fence projects in Spokane typically range from $50 – $200. Fees are usually based on the estimated project value.

Typical approval time in Spokane is about 2 weeks. Complex projects requiring structural review may take longer.

In most cases, homeowners in Spokane can pull permits and perform work on their own primary residence as an owner-builder. You're still responsible for meeting all code requirements and passing inspections.

Working without a required permit in Spokane can result in fines, stop-work orders, required removal of completed work, and complications when selling your home.

Ready to check your fence project in Spokane?

Use our free lookup tool to get a personalized answer based on your specific project details.

Free Permit Lookup →

Fence Permits in Nearby Cities

See fence permit requirements in other Washington cities:

See Detailed Fence Rules for Spokane

View all local rules, exemptions, and fee details on the permit page.

Fence Permit Rules →
Disclaimer: This guide provides general information about fence permit requirements in Spokane, WA. Requirements can change. Always confirm with Development Services Center before starting any project. PermitMint provides general guidance, not legal advice.