Do You Need a Demolition Permit in San Francisco?

Based on San Francisco's local building codes, you'll need a permit when:

Required·Rule 1

Full building demolition requires a demolition permit. All utilities (gas, electric, water, sewer) must be disconnected before work begins. An asbestos survey is required for structures built before 1978.

SourceCalifornia Building Code / 2022 IRC with local amendments
Required·Rule 2

Demolition of structures built before 1978 requires a permit and an asbestos survey before any work begins. Federal EPA NESHAP regulations require asbestos-containing materials to be identified and properly abated. Lead paint may also be present and require special handling.

SourceCalifornia Building Code / 2022 IRC with local amendments
Required·Rule 3

Partial demolition that involves removing structural elements (walls, roof sections, floors) requires a building permit. Structural plans may be required showing how the remaining structure will be supported.

SourceCalifornia Building Code / 2022 IRC with local amendments

These demolition projects are typically exempt in San Francisco:

Exempt·Rule 1

Removing a small accessory structure (shed, carport, small outbuilding) built after 1978 and not in a historic district may be exempt from a demolition permit. However, utility disconnection and proper disposal are still required. Check with your building department.

SourceCalifornia Building Code / 2022 IRC with local amendments

Permit Fees in San Francisco

Based on local San Francisco permit data, fees for demolition projects typically range:

$150 – $1,500 San Francisco Permit Fee Range

Here's how fees break down by project scope nationally:

Project ScopeTypical Permit Fee
Small accessory structure removal (where permit needed)$50 – $200
Interior demolition / gutting permit$100 – $500
Partial structural demolition$150 – $500
Full residential building demolition$200 – $1,000+
Asbestos survey (pre-1978 structures)$300 – $800 (separate from permit)
Asbestos abatement (if ACM found)$1,500 – $15,000+ (separate from permit)

Fees are typically calculated based on estimated project value. Contact Department of Building Inspection (DBI) for exact amounts.

How Long Does It Take?

In San Francisco, typical approval time for demolition permits is about 3 weeks.

More complex projects requiring structural review or variances may take longer. Simple projects may qualify for expedited or over-the-counter review in some cases.

How to Apply for a Demolition Permit in San Francisco

  1. 1 Check requirements: Use our free lookup tool or contact Department of Building Inspection (DBI) to confirm your project needs a permit.
  2. 2 Gather documents: Prepare your application, site plan, construction drawings, and any other required documents.
  3. 3 Submit online: San Francisco accepts applications online at Department of Building Inspection (DBI).
  4. 4 Pay fees: Pay the applicable permit fees ($150 – $1,500).
  5. 5 Wait for approval: Your application will be reviewed by San Francisco plan reviewers. Typical turnaround is about 3 weeks.
  6. 6 Begin work: Once approved, post your permit visibly at the job site before starting work.
  7. 7 Schedule inspections: Call Department of Building Inspection (DBI) at (628) 652-3200 to schedule required inspections at each phase of the project.

San Francisco Building Department Contact

NameDepartment of Building Inspection (DBI)
Apply OnlineApply online
Address49 South Van Ness Ave., San Francisco, CA 94103
HoursMon 9am-5pm, Tue-Fri 8am-5pm

Required Inspections in San Francisco

Most demolition projects in San Francisco require inspections at each construction stage:

Inspection·Stage 1

Pre-Demolition Inspection, Utilities are confirmed disconnected (gas, electric, water, sewer), asbestos abatement is complete (for pre-1978 structures), demolition permit is posted, erosion control measures are in place, and the contractor has proper equipment and safety measures.

WhenBefore demolition work begins, may be required to verify utility disconnection and asbestos abatement completion
Common FailuresUtilities not fully disconnected, asbestos abatement not completed or documented, erosion control not installed.
Inspection·Stage 2

Final Site Inspection, All structures fully removed, basement or foundation properly filled and compacted, site graded to drain properly (not toward neighboring properties), debris removed, erosion control in place, and the site is safe and stable.

WhenAfter demolition is complete and the site has been cleared and graded
Common FailuresFoundation not filled or improperly compacted, site not graded (water pooling), debris remaining, erosion control missing.

Schedule inspections with Department of Building Inspection (DBI) at (628) 652-3200 at least 24–48 hours in advance.

Frequently Asked Questions

Whether you need a permit depends on the size and scope of your demolition project. In San Francisco, some smaller projects are exempt while larger ones require a permit. Use our free lookup tool to check your specific situation.

Permit fees for demolition projects in San Francisco typically range from $150 – $1,500. Fees are usually based on the estimated project value.

Typical approval time in San Francisco is about 3 weeks. Complex projects requiring structural review may take longer.

In most cases, homeowners in San Francisco can pull permits and perform work on their own primary residence as an owner-builder. You're still responsible for meeting all code requirements and passing inspections.

Working without a required permit in San Francisco can result in fines, stop-work orders, required removal of completed work, and complications when selling your home.

Ready to check your demolition project in San Francisco?

Use our free lookup tool to get a personalized answer based on your specific project details.

Free Permit Lookup →

Demolition Permits in Nearby Cities

See demolition permit requirements in other California cities:

See Detailed Demolition Rules for San Francisco

View all local rules, exemptions, and fee details on the permit page.

Demolition Permit Rules →
Disclaimer: This guide provides general information about demolition permit requirements in San Francisco, CA. Requirements can change. Always confirm with Department of Building Inspection (DBI) before starting any project. PermitMint provides general guidance, not legal advice.