Shed Permit Requirements in Sharon, WI

Walworth County village. Note: a separate Town of Sharon also exists with its own inspector contact. For the Village, the Building Inspector / Zoning Administrator is Jerry Anderson (262-903-1221); Code Enforcement Officer is Allison Schwark (262-249-6701). Village Hall main numbers are 262-736-4888 / 262-736-4889. No third-party inspection agency (SafeBuilt/IIL/GEC) named; inspector appears to be an independent DSPS-certified contractor working directly for the Village. No online permit portal documented; permit applications are paper forms via villageofsharon.com/forms-permits/.

By Joey, Founder · Last verified May 15, 2026 · How we research →

Code: 2015 Verified: 2026-05-15 1 local rules

When you don’t need a Shed permit in Sharon

Exempt·Rule 1

Sheds and outbuildings 200 sq ft or less are typically exempt from a building permit but still must meet zoning setbacks (commonly 3 to 5 feet from property line) and lot-coverage limits. Sheds over 200 sq ft or with utilities require a permit. Some HOAs ban sheds outright. To confirm requirements for your specific project in Sharon, WI, contact Village of Sharon Building, Zoning & Code Enforcement at (262) 736-4888. Visit: https://villageofsharon.com/building-zoning-code-enforcement/.

SourceVillage of Sharon Building, Zoning & Code Enforcement — phone (262) 736-4888 · view source

Shed Permit Costs: Sharon vs. Nearby

CityEstimated Fee
Sharon N/A
Milwaukee $50 – $300
Madison $50 – $300
Green Bay $50 – $300

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Sharon permit costs →

Zoning Considerations

Zoning

Sheds may be subject to zoning setback requirements and lot coverage limits. Placement near property lines or in front yards may require zoning approval.

Estimated Project Timeline in Sharon

Here's a typical timeline for a shed project in Sharon, WI:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings.
Week 2
Submit permit application
Your contractor submits the application to Sharon's building department.
Week 3-4
Plan review & approval
Processing time varies, contact Sharon's building department for current turnaround times.
Week 5+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Need a Shed permit in Sharon, WI?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameVillage of Sharon Building, Zoning & Code Enforcement
Address125 Plain Street, PO Box 379, Sharon, WI 53585
HoursMon-Fri 8:00am-4:30pm

Frequently Asked Questions

Contact Sharon's building department for current Shed permit fee information. Fees typically vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Shed projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Sharon can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Contact Sharon's building department for current processing times. Timelines vary based on project complexity and whether plan review is required.

Learn More About Shed Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Shed Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-05-15. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.