Bristol Kenosha County (not Bristol Dane County). On WI DSPS delegated-municipality list, entry 415. Village Administrator Randy Kerkman is the dept contact per DSPS. Kenosha County zoning excludes Bristol (village governs its own). Not shared with neighboring Salem Lakes village. Online portal: InspectWiz. WI enforces its own UDC for 1-2 family homes.

By Joey, Founder · Last verified May 28, 2026 · How we research →

Population: 5,000 Code: 2021 Verified: 2026-05-28 1 local rules

When you need a Pool & Hot Tub permit

Required·Rule 1

An in-ground pool requires a UDC building permit (SPS 321) and an electrical permit (SPS 316, NEC 680 equipotential bonding) from the Village of Bristol Building Inspection via InspectWiz. Pool barrier fencing 48 inches minimum with self-closing, self-latching gate per IRC R326 is required. DSPS Master Electrician license required for the bonding and dedicated pump/heater circuits. Verify Village of Bristol zoning setbacks at 262-857-2368.

Typical Timelineabout 2 weeks
SourceVillage of Bristol Building Inspection / WI UDC SPS 321 + SPS 316 / NEC 680 · view source

Swimming Pool, Hot Tub, or Spa Permit Costs: Bristol vs. Nearby

CityEstimated Fee
Bristol N/A
Milwaukee $100 – $1,500
Madison $100 – $1,500
Green Bay $100 – $1,500

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Bristol permit costs →

Zoning Considerations

Zoning

Pools may require zoning approval for setback compliance. Many jurisdictions have minimum distance requirements from property lines and easements.

Estimated Project Timeline

Here's a typical timeline for a swimming pool, hot tub, or spa project:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Bristol's building department, apply online here.
Week 4-5
Plan review & approval
Typical processing time: about 2 weeks. Plan review examiner checks drawings for code compliance.
Week 6+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on the typical about 2 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Pool & Hot Tub permit?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameVillage of Bristol Building Inspection Department
Address19801 83rd Street, Bristol, WI 53104
HoursMon-Fri 8am-4pm Village Hall; inspections Tue and Thu mornings, 24hr notice required

Frequently Asked Questions

Contact the building department for current Swimming Pool, Hot Tub, or Spa permit fee information. Fees typically vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Swimming Pool, Hot Tub, or Spa projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Swimming Pool, Hot Tub, or Spa permits is about 2 weeks. More complex projects may take longer if plan review is required.

Learn More About Swimming Pool, Hot Tub, or Spa Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Swimming Pool, Hot Tub, or Spa Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-05-28. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.