Patio Permit Requirements in Bristol, WI

Bristol Kenosha County (not Bristol Dane County). On WI DSPS delegated-municipality list, entry 415. Village Administrator Randy Kerkman is the dept contact per DSPS. Kenosha County zoning excludes Bristol (village governs its own). Not shared with neighboring Salem Lakes village. Online portal: InspectWiz. WI enforces its own UDC for 1-2 family homes.

By Joey, Founder · Last verified May 28, 2026 · How we research →

Population: 5,000 Code: 2021 Verified: 2026-05-28 1 local rules

When you don’t need a Patio permit

Exempt·Rule 1

An at-grade patio (paver, concrete, or flagstone) is generally exempt from a UDC building permit per SPS 320.07 because it is not a structure under the dwelling code. Zoning setbacks still apply, verify with Village of Bristol at 262-857-2368.

SourceVillage of Bristol Building Inspection / WI UDC SPS 320.07 · view source

Patio Permit Costs: Bristol vs. Nearby

CityEstimated Fee
Bristol N/A
Milwaukee $100 – $500
Madison $100 – $500
Green Bay $100 – $500

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Bristol permit costs →

Zoning Considerations

Zoning

Patios contribute to impervious surface coverage on your lot. Many cities cap total impervious coverage at 40–60% of lot area. Check with your planning department before adding large hardscape areas.

Estimated Project Timeline

Here's a typical timeline for a patio project:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings.
Week 2
Submit permit application
Your contractor submits the application to Bristol's building department, apply online here.
Week 3-4
Plan review & approval
Processing time varies, contact Bristol's building department for current turnaround times.
Week 5+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Need a Patio permit?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameVillage of Bristol Building Inspection Department
Address19801 83rd Street, Bristol, WI 53104
HoursMon-Fri 8am-4pm Village Hall; inspections Tue and Thu mornings, 24hr notice required

Frequently Asked Questions

Contact the building department for current Patio permit fee information. Fees typically vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Patio projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Contact the building department for current processing times. Timelines vary based on project complexity and whether plan review is required.

Learn More About Patio Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Patio Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-05-28. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.