Bathroom Remodel Permit Requirements in Humble, TX

CORRECTION: AHJ changed from Harris County to the City of Humble. Inside Humble city limits the City of Humble Building & Inspection Department (114 W. Higgins St, Chief Building Official Ray Pearson, 281-446-6228) is the correct AHJ; Harris County's Office of the County Engineer Permits Division regulates only unincorporated areas. Texas has no statewide residential code; Humble adopted the 2018 IRC (Code of Ordinances Ch. 4, Art. 4.02) plus 2018 IBC/IPC/IMC/IFC, 2017 NEC, and 2018 Energy Code. Permits filed via the iWorq portal, though most plan-review permits must be submitted in person. Residential fees from the official Oct 1, 2024 fee schedule: Building Permit $50.00 + $0.32/sq ft of roof-covered floor space; Fence $50.00 + $1.00/25 LF; Electrical $50-$150; Plumbing $50-$100.

By Joey, Founder · Last verified May 31, 2026 · How we research →

Population: 16,795 Code: 2018 IRC Verified: 2026-05-31 1 local rules

When you need a Bathroom permit

Required·Rule 1

Inside the City of Humble, a bathroom remodel that alters plumbing, electrical, or structure requires permits from the City of Humble Building & Inspection Department under the 2018 IRC and 2017 NEC. Cosmetic-only work in the existing fixture locations is generally exempt. The residential plumbing permit for a remodel/addition is $100.00 (or $50.00 minimum for limited work) and the residential electrical remodel/addition permit is $100.00 per the Oct 1, 2024 fee schedule.

Estimated Fee$50 – $100
Typical Timelineabout 2 weeks
SourceCity of Humble Building & Inspection Dept / Code of Ordinances Ch. 4 Art. 4.02 (2018 IRC) / Permit Fee Schedule eff. Oct 1, 2024 · view source

Bathroom Remodel Permit Costs: Humble vs. Nearby

Humble comes in on the low side for Texas. You're looking at $50 – $100 here, compared to the state average of $126 – $434.

CityEstimated Fee
Humble $50 – $100
Houston $50 – $700
San Antonio $40 – $595
Dallas $50 – $700

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Humble permit costs →

Zoning & HOA Considerations

HOA Communities

If you live in an HOA community: interior bathroom remodels rarely require HOA approval. However, if the work involves exterior changes (new vents, windows, or plumbing cleanouts), check your CC&Rs first.

Estimated Project Timeline

Here's a typical timeline for a bathroom remodel project:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings.
Week 2
Submit permit application
Your contractor submits the application to Humble's building department, apply online here.
Week 3-4
Plan review & approval
Typical processing time: about 2 weeks. Application review and permit issuance.
Week 5+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on the typical about 2 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Bathroom permit?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameCity of Humble Building & Inspection Department
Address114 W. Higgins St, Humble, TX 77338
HoursMon-Fri 7:30am-4:30pm

Frequently Asked Questions

Estimated permit fees for Bathroom Remodel projects range from $50 – $100. Fees vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Bathroom Remodel projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Bathroom Remodel permits is about 2 weeks. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Bathroom Remodel Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Bathroom Remodel Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-05-31. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.