Kitchen Remodel Permit Requirements in Soddy-Daisy, TN

City in Hamilton County, part of the Chattanooga metro area. Tennessee follows state-adopted building codes based on the IRC 2018 cycle.

By Joey, Founder · Last verified March 29, 2026 · How we research →

Population: 13,510 Code: 2018 Verified: 2026-03-29 5 local rules

When you don’t need a Kitchen permit in Soddy-Daisy

Exempt·Rule 1

Cosmetic kitchen updates such as paint, cabinets, and countertops without gas work do not require a permit.

SourceTennessee State Building Code / 2021 IRC · view source

When you need a Kitchen permit in Soddy-Daisy

Required·Rule 1

Kitchen remodels involving plumbing changes such as moving the sink require permits.

Estimated Fee$150 – $550
Typical Timelineabout 2 weeks
SourceTennessee State Building Code / 2021 IRC · view source
Required·Rule 2

Removing or moving kitchen walls requires a building permit.

Estimated Fee$150 – $550
Typical Timelineabout 2 weeks
SourceTennessee State Building Code / 2021 IRC · view source
Required·Rule 3

Adding a kitchen island with utilities requires building, plumbing, and electrical permits.

Estimated Fee$325 – $1,000
Typical Timelineabout 2 weeks
SourceTennessee State Building Code / 2021 IRC · view source
Required·Rule 4

Any gas line work in a kitchen requires a mechanical permit.

Estimated Fee$55 – $175
Typical Timeline5 business days
SourceTennessee State Building Code / 2021 IRC · view source

Kitchen Remodel Permit Costs: Soddy-Daisy vs. Nearby

Soddy-Daisy comes in on the low side for Tennessee. You're looking at $55 – $1,000 here, compared to the state average of $197 – $642.

CityEstimated Fee
Soddy-Daisy $55 – $1,000
Nashville $200 – $1,200
Memphis $200 – $1,200
Knoxville $200 – $1,200

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Soddy-Daisy permit costs →

Zoning & HOA Considerations

HOA Communities

If you live in an HOA community: interior kitchen remodels typically don't require HOA approval. If exterior changes are involved (new exhaust vents, windows, or gas line routing), check your CC&Rs.

Estimated Project Timeline in Soddy-Daisy

Here's a typical timeline for a kitchen remodel project in Soddy-Daisy, TN:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Soddy-Daisy's building department, apply online here.
Week 4-5
Plan review & approval
Typical processing time in Soddy-Daisy: about 2 weeks. Plan review examiner checks drawings for code compliance.
Week 6+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Soddy-Daisy's typical about 2 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Kitchen permit in Soddy-Daisy, TN?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameSoddy-Daisy Building & Permits
Address9835 Dayton Pike, Soddy-Daisy, TN 37379
HoursMon-Fri 8am-4pm

Frequently Asked Questions

Estimated permit fees for Kitchen Remodel projects in Soddy-Daisy, TN range from $55 – $1,000. Fees vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Kitchen Remodel projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Soddy-Daisy can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Kitchen Remodel permits in Soddy-Daisy is about 2 weeks. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Kitchen Remodel Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Kitchen Remodel Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-03-29. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.