Kitchen Remodel Permit Requirements in Memphis, TN

Tennessee does not have a statewide building code; Memphis enforces locally adopted 2018 IRC.

By Joey, Founder · Last verified April 7, 2026 · How we research →

Population: 633,104 Code: 2018 Verified: 2026-04-07 3 local rules

When you don’t need a Kitchen permit in Memphis

Exempt·Rule 1

Replacing a kitchen appliance in the same location with the same fuel type does not require a permit.

SourceMemphis & Shelby County Building Codes / 2018 IRC

When you need a Kitchen permit in Memphis

Required·Rule 1

Kitchen remodels involving plumbing, electrical, or gas changes require permits.

Estimated Fee$200 – $700
Typical Timelineabout 2 weeks
SourceMemphis & Shelby County Building Codes / 2018 IRC
Required·Rule 2

Adding a new kitchen requires building, plumbing, electrical, and mechanical permits.

Estimated Fee$400 – $1,200
Typical Timelineabout 3 weeks
SourceMemphis & Shelby County Building Codes / 2018 IRC

Kitchen Remodel Permit Costs: Memphis vs. Nearby

Memphis's fees are right in line with the Tennessee average, $200 – $1,200 versus $197 – $642 statewide.

CityEstimated Fee
Memphis $200 – $1,200
Nashville $200 – $1,200
Knoxville $200 – $1,200
Chattanooga $200 – $1,200

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Memphis permit costs →

Zoning & HOA Considerations

HOA Communities

If you live in an HOA community: interior kitchen remodels typically don't require HOA approval. If exterior changes are involved (new exhaust vents, windows, or gas line routing), check your CC&Rs.

Estimated Project Timeline in Memphis

Here's a typical timeline for a kitchen remodel project in Memphis, TN:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Memphis's building department, apply online here.
Week 4-7
Plan review & approval
Typical processing time in Memphis: about 3 weeks. Plan review examiner checks drawings for code compliance.
Week 8+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Memphis's typical about 3 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Kitchen permit in Memphis, TN?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameOffice of Construction Code Enforcement
Address6465 Mullins Station Rd., Memphis, TN 38134
HoursMon-Fri 7:30am-4pm

Frequently Asked Questions

Estimated permit fees for Kitchen Remodel projects in Memphis, TN range from $200 – $1,200. Fees vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Kitchen Remodel projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Memphis can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Kitchen Remodel permits in Memphis is about 2 weeks. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Kitchen Remodel Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Kitchen Remodel Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-04-07. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.