Deck Permit Requirements in Collierville, TN

Collierville is a city of 52,894 residents in Tennessee that follows the 2021 IRC. For deck projects, Collierville follows the IRC pretty closely, no major surprises compared to what most cities require. You're looking at roughly $90 – $315 in permit fees, plan on about 2 weeks for approval, plus you can apply online.

By Joey, Founder · Last verified March 29, 2026 · How we research →

Population: 52,894 Code: 2021 Verified: 2026-03-29 4 local rules

When you don’t need a Deck permit in Collierville

Exempt·Rule 1

Freestanding decks under 30 inches are exempt.

SourceTennessee Building Code / 2021 IRC

When you need a Deck permit in Collierville

Required·Rule 1

Attached decks require a permit.

Estimated Fee$90 – $315
Typical Timelineabout 2 weeks
SourceTennessee Building Code / 2021 IRC
Required·Rule 2

Decks over 30 inches require a permit.

Estimated Fee$135 – $450
Typical Timelineabout 2 weeks
SourceTennessee Building Code / 2021 IRC
Required·Rule 3

Covered decks over 300 sq ft require a permit.

Estimated Fee$180 – $540
Typical Timelineabout 3 weeks
SourceTennessee Building Code / 2021 IRC

What Makes Collierville Different

Here's how Collierville's deck rules stack up against the standard IRC baseline that most of the country follows.

Stricter Than the IRC

Attached decks require a permit.

Decks over 30 inches require a permit.

1 rule match the IRC baseline, no surprises there.

Deck Permit Costs: Collierville vs. Nearby

Collierville comes in on the low side for Tennessee. You're looking at $90 – $540 here, compared to the state average of $124 – $407.

CityEstimated Fee
Collierville $90 – $540
Nashville $100 – $600
Memphis $100 – $600
Knoxville $100 – $600

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Collierville permit costs →

Zoning & HOA Considerations

Zoning

Decks may be subject to zoning setback and lot coverage requirements. Check with your local planning department before building near property lines.

HOA Communities

If you live in an HOA community: many HOAs restrict deck materials, colors, size, and placement. Review your CC&Rs and submit an architectural review request before applying for a building permit. HOA approval can take 1–6 weeks.

Estimated Project Timeline in Collierville

Here's a typical timeline for a deck project in Collierville, TN:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Collierville's building department, apply online here.
Week 4-6
Plan review & approval
Typical processing time in Collierville: about 3 weeks. Plan review examiner checks drawings for code compliance.
Week 7+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Collierville's typical about 3 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Deck permit in Collierville, TN?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameCollierville Building Department
Address500 Poplar View Pkwy, Collierville, TN 38017
HoursMon-Fri 8am-5pm

Frequently Asked Questions

Estimated permit fees for Deck projects in Collierville, TN range from $90 – $540. Fees vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Deck projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Collierville can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Deck permits in Collierville is about 2 weeks. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Deck Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Deck Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-03-29. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.