Moore is an unincorporated community in southwestern Spartanburg County, SC, located south of Spartanburg on U.S. Route 221, one mile west of I-26 (I-26 corridor), in the Tyger River watershed. AHJ is Spartanburg County Building Codes (Department 26 on the county directory). SAME AHJ shared with other unincorporated Spartanburg County communities including Lyman and Woodruff. Online permitting via EnerGov Citizen Self Service (CSS) at civicaccess.spartanburgcounty.gov. SC adopts the 2021 IRC with SC amendments effective 2024-01-01 via the SC Building Codes Council. ASCE 7 wind zone, ASHRAE Climate Zone 3A. Population (16,007) is the 2020 Census total for ZIP 29369, not Moore community alone (Moore is an unincorporated community without a CDP).

By Joey, Founder · Last verified May 23, 2026 · How we research →

Population: 16,007 Code: 2021 IRC + SC amendments Verified: 2026-05-23 1 local rules

When you need a Fireplace permit in Moore

Required·Rule 1

SC (unincorporated Spartanburg County), a new solid-fuel (wood-burning) fireplace or gas fireplace installation requires a building permit from Spartanburg County Building Codes. Masonry fireplaces follow 2021 IRC Chapter 10; factory-built units must be UL/ULC listed and installed per listing. Gas units also trigger gas-line inspection.

Typical Timelineabout 2 weeks
SourceSpartanburg County Building Codes / 2021 IRC Chapter 10 · view source

Fireplace Permit Costs: Moore vs. Nearby

CityEstimated Fee
Moore N/A
York County $0
Charleston $75 – $800
Columbia $75 – $800

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Moore permit costs →

Zoning & HOA Considerations

Zoning

Fireplace and wood stove installations rarely trigger zoning review. Many California air quality districts (SCAQMD, BAAQMD) prohibit NEW wood-burning fireplaces in new construction. Chimney height requirements must comply with IRC R1003.9 (3 ft above roof penetration, 2 ft above any point within 10 ft horizontally).

HOA Communities

If you live in an HOA community: hOAs in some communities prohibit wood-burning appliances entirely due to smoke and air quality concerns. Gas fireplaces are usually permitted. Chimney caps and exterior venting may face aesthetic review.

Estimated Project Timeline in Moore

Here's a typical timeline for a fireplace project in Moore, SC:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Moore's building department, apply online here.
Week 4-5
Plan review & approval
Typical processing time in Moore: about 2 weeks. Plan review examiner checks drawings for code compliance.
Week 6+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Moore's typical about 2 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Fireplace permit in Moore, SC?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameSpartanburg County Building Codes
Address366 N Church St, Main Level, Suite 500, Spartanburg, SC 29303
HoursOffice: Monday-Friday 8:00 AM to 4:30 PM. Permitting: Monday-Friday 8:00 AM to 4:00 PM. Inspectors: Monday-Friday 7:30 AM to 4:00 PM.

Frequently Asked Questions

Contact Moore's building department for current Fireplace permit fee information. Fees typically vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Fireplace projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Moore can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Fireplace permits in Moore is about 2 weeks. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Fireplace Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Fireplace Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-05-23. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.