Fireplace Permit Requirements in Forest Grove, OR

City runs its own delegated building program (Forest Grove/Cornelius Building Division) and issues structural, mechanical, and plumbing permits enforcing the statewide Oregon specialty codes; permits pulled through the State of Oregon ePermitting (Accela) portal. Verified exemption thresholds: deck exempt if not over 30 in above grade and 5 ft from property lines; fence exempt if not over 6 ft (pool barriers regulated); accessory building exempt if not over 200 sq ft (or frame-covered up to 500 sq ft, one story, 5 ft from lines); reroof exempt if not over 30% of live-load capacity and not required to be fire-resistant. Office hours not published online.

By Joey, Founder · Last verified May 31, 2026 · How we research →

Code: 2023 Oregon Residential Specialty Code (ORSC); 2022 Oregon Structural Specialty Code (2025 OSSC effective Apr 1, 2026); Oregon Plumbing and Mechanical Specialty Codes. City adopts the statewide Oregon specialty codes by reference per FG Code 150.003. Verified: 2026-05-31 1 local rules

When you need a Fireplace permit

Required·Rule 1

Installing a new fireplace, wood stove, or gas insert requires a building permit (and a gas permit for a gas appliance), enforced by the City of Forest Grove Building Division under the Oregon specialty codes. Clearance to combustibles, hearth extension, and chimney termination per the 2023 ORSC apply. A carbon monoxide alarm is required near sleeping areas. Apply through the State of Oregon ePermitting (Accela) portal.

Typical Timelineabout 2 weeks
SourceCity of Forest Grove Building Division / 2023 Oregon Residential Specialty Code (ORSC) · view source

Fireplace Permit Costs: Forest Grove vs. Nearby

CityEstimated Fee
Forest Grove N/A
Portland $75 – $800
Lane County $75 – $800
Salem $75 – $800

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Forest Grove permit costs →

Zoning Considerations

Zoning

Fireplace and wood stove installations rarely trigger zoning review. Many California air quality districts (SCAQMD, BAAQMD) prohibit NEW wood-burning fireplaces in new construction. Chimney height requirements must comply with IRC R1003.9 (3 ft above roof penetration, 2 ft above any point within 10 ft horizontally).

Estimated Project Timeline

Here's a typical timeline for a fireplace project:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Forest Grove's building department, apply online here.
Week 4-5
Plan review & approval
Typical processing time: about 2 weeks. Plan review examiner checks drawings for code compliance.
Week 6+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on the typical about 2 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Fireplace permit?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameCity of Forest Grove Building Division (Community Development Dept.)
AddressCity of Forest Grove, 1924 Council Street, Forest Grove, OR 97116

Frequently Asked Questions

Contact the building department for current Fireplace permit fee information. Fees typically vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Fireplace projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Fireplace permits is about 2 weeks. More complex projects may take longer if plan review is required.

Learn More About Fireplace Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Fireplace Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-05-31. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.