Shed Permit Requirements in Cherry Hill, NJ

Cherry Hill is a city of 74,553 residents in New Jersey that follows the 2018 IRC. Cherry Hill's building department is stricter than the standard IRC on shed work, expect fewer exemptions and more situations that require a permit. You're looking at roughly $75 – $250 in permit fees, plan on about 2 weeks for approval, plus you can apply online.

By Joey, Founder · Last verified March 29, 2026 · How we research →

Population: 74,553 Code: 2018 Verified: 2026-03-29 3 local rules

When you don’t need a Shed permit in Cherry Hill

Exempt·Rule 1

Structures 120 sq ft or less are exempt.

SourceNew Jersey UCC / 2018 IRC · view source

When you need a Shed permit in Cherry Hill

Required·Rule 1

Structures over 120 sq ft require a permit.

Estimated Fee$75 – $250
Typical Timelineabout 2 weeks
SourceNew Jersey UCC / 2018 IRC · view source
Required·Rule 2

Sheds with electrical require a permit.

Estimated Fee$50 – $150
Typical Timelineabout 1 week
SourceNew Jersey UCC / 2018 IRC · view source

Shed Permit Costs: Cherry Hill vs. Nearby

Cherry Hill comes in on the low side for New Jersey. You're looking at $50 – $250 here, compared to the state average of $66 – $239.

CityEstimated Fee
Cherry Hill $50 – $250
Newark $70 – $420
Jersey City $90 – $540
Paterson $50 – $300

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Cherry Hill permit costs →

Real Shed Permit Data for Cherry Hill

From our own dataset of permits filed in Cherry Hill over the last 3 years.

37
shed permits filed
$168
typical fee paid (median)

These figures reflect actual permits issued in Cherry Hill, not state averages or estimates. Your project may differ based on scope, valuation, and the specific work proposed.

Zoning & HOA Considerations

Zoning

Sheds may be subject to zoning setback requirements and lot coverage limits. Placement near property lines or in front yards may require zoning approval.

HOA Communities

If you live in an HOA community: many HOAs restrict or prohibit outbuildings. Check your CC&Rs for rules on shed size, placement, materials, and appearance before purchasing or building.

Estimated Project Timeline in Cherry Hill

Here's a typical timeline for a shed project in Cherry Hill, NJ:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Cherry Hill's building department, apply online here.
Week 4-5
Plan review & approval
Typical processing time in Cherry Hill: about 2 weeks. Plan review examiner checks drawings for code compliance.
Week 6+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Cherry Hill's typical about 2 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Shed permit in Cherry Hill, NJ?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameCherry Hill Building Department
Address820 Mercer St, Cherry Hill, NJ 08002
HoursMon-Fri 8:30am-4:30pm

Frequently Asked Questions

Estimated permit fees for Shed projects in Cherry Hill, NJ range from $50 – $250. Fees vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Shed projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Cherry Hill can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Shed permits in Cherry Hill is about 2 weeks. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Shed Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Shed Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-03-29. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.