Fence Permit Requirements in Billings, MT

Montana adopted the 2021 IRC effective June 2022. Plans to adopt 2024 codes in mid-2026.

By Joey, Founder · Last verified March 28, 2026 · How we research →

Population: 119,500 Code: 2021 Verified: 2026-03-28 5 local rules

When you don’t need a Fence permit in Billings

Exempt·Rule 1

Backyard fences 6 feet or under do not require a building permit.

SourceCity of Billings / Montana Building Code / 2021 IRC · view source
Exempt·Rule 2

Front yard fences 4 feet or under do not require a building permit.

SourceCity of Billings / Montana Building Code / 2021 IRC · view source

When you need a Fence permit in Billings

Required·Rule 1

Fences over 6 feet require a building permit.

Estimated Fee$50 – $150
Typical Timelineabout 1 week
SourceCity of Billings / Montana Building Code / 2021 IRC · view source
Required·Rule 2

Masonry or concrete fences require a building permit regardless of height.

Estimated Fee$75 – $200
Typical Timelineabout 2 weeks
SourceCity of Billings / Montana Building Code / 2021 IRC · view source
Required·Rule 3

Pool barrier fencing must meet IRC/local pool safety code and requires a permit.

Estimated Fee$50 – $150
Typical Timelineabout 1 week
SourceCity of Billings / Montana Building Code / 2021 IRC · view source

What Makes Billings Different

Here's how Billings's fence rules stack up against the standard IRC baseline that most of the country follows.

Stricter Than the IRC

Billings drops the height feet threshold to 6 feet. The IRC allows up to 7 feet before requiring a permit.

Billings drops the height feet threshold to 4 feet. The IRC allows up to 7 feet before requiring a permit.

Fences over 6 feet require a building permit.

Masonry or concrete fences require a building permit regardless of height.

1 rule match the IRC baseline, no surprises there.

Fence Permit Costs: Billings vs. Nearby

Billings's fees are right in line with the Montana average, $50 – $200 versus $43 – $130 statewide.

CityEstimated Fee
Billings $50 – $200
Missoula $52 – $210
Great Falls $45 – $180
Bozeman $55 – $220

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Billings permit costs →

Zoning & HOA Considerations

Zoning

Front-yard fences and fences above certain heights may require zoning approval. Many cities limit front-yard fence height to 3–4 feet. Check setback and height limits with your planning department.

HOA Communities

If you live in an HOA community: hOAs frequently restrict fence materials, colors, heights, and styles, often more strictly than city code. Review your CC&Rs and submit to your Architectural Review Committee (ARC) before applying for a city permit.

Estimated Project Timeline in Billings

Here's a typical timeline for a fence project in Billings, MT:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Billings's building department, apply online here.
Week 4-5
Plan review & approval
Typical processing time in Billings: about 2 weeks. Plan review examiner checks drawings for code compliance.
Week 6+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Billings's typical about 2 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Fence permit in Billings, MT?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameCity of Billings Building Division
Address316 N 26th St, 5th Floor, Billings, MT 59101
HoursMon-Fri 9:00am-5:00pm

Frequently Asked Questions

Estimated permit fees for Fence projects in Billings, MT range from $50 – $200. Fees vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Fence projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Billings can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Fence permits in Billings is about 1 week. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Fence Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Fence Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-03-28. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.