Demolition Permit Requirements in Red Wing, MN

Red Wing is a mid-size city of 16,722 residents in Minnesota that follows the 2018 IRC. Red Wing's building department is stricter than the standard IRC on demolition work, expect fewer exemptions and more situations that require a permit. You're looking at roughly $200 – $1,000 in permit fees, plan on about 3 weeks for approval, plus you can apply online.

By Joey, Founder · Last verified March 29, 2026 · How we research →

Population: 16,722 Code: 2018 Verified: 2026-03-29 4 local rules

When you don’t need a Demolition permit in Red Wing

Exempt·Rule 1

Removing a small accessory structure (shed, carport, small outbuilding) built after 1978 and not in a historic district may be exempt from a demolition permit. However, utility disconnection and proper disposal are still required. Check with your building department.

SourceMinnesota Building Code / 2018 IRC with local amendments

When you need a Demolition permit in Red Wing

Required·Rule 1

Full building demolition requires a demolition permit. All utilities (gas, electric, water, sewer) must be disconnected before work begins. An asbestos survey is required for structures built before 1978.

Estimated Fee$200 – $1,000
Typical Timelineabout 3 weeks
SourceMinnesota Building Code / 2018 IRC with local amendments
Required·Rule 2

Demolition of structures built before 1978 requires a permit and an asbestos survey before any work begins. Federal EPA NESHAP regulations require asbestos-containing materials to be identified and properly abated. Lead paint may also be present and require special handling.

Estimated Fee$200 – $800
Typical Timelineabout 3 weeks
SourceMinnesota Building Code / 2018 IRC with local amendments
Required·Rule 3

Partial demolition that involves removing structural elements (walls, roof sections, floors) requires a building permit. Structural plans may be required showing how the remaining structure will be supported.

Estimated Fee$100 – $500
Typical Timelineabout 2 weeks
SourceMinnesota Building Code / 2018 IRC with local amendments

Demolition Permit Costs: Red Wing vs. Nearby

Red Wing comes in on the low side for Minnesota. You're looking at $100 – $1,000 here, compared to the state average of $164 – $758.

CityEstimated Fee
Red Wing $100 – $1,000
Minneapolis $100 – $1,000
St. Paul $100 – $1,000
Rochester $100 – $1,000

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Red Wing permit costs →

Zoning & HOA Considerations

Zoning

Properties in historic districts may require historic review board approval before demolition. Some cities require a waiting period for demolition permits to allow for public comment.

HOA Communities

If you live in an HOA community: demolition of visible structures (garages, sheds, accessory buildings) may require HOA notification or approval. Check your CC&Rs, some communities require maintaining certain structures or replacing them within a set timeframe.

Estimated Project Timeline in Red Wing

Here's a typical timeline for a demolition project in Red Wing, MN:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Red Wing's building department, apply online here.
Week 4-6
Plan review & approval
Typical processing time in Red Wing: about 3 weeks. Plan review examiner checks drawings for code compliance.
Week 7+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Red Wing's typical about 3 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Demolition permit in Red Wing, MN?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameRed Wing Building Department
Address315 W 4th St, Red Wing, MN 55066
HoursMon-Fri 8am-4:30pm

Frequently Asked Questions

Estimated permit fees for Demolition projects in Red Wing, MN range from $100 – $1,000. Fees vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Demolition projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Red Wing can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Demolition permits in Red Wing is about 3 weeks. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Demolition Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Demolition Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-03-29. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.