Fence Permit Requirements in Princess Anne, MD

Princess Anne is a small town of 3,616 residents in Maryland that follows the 2018 IRC. Princess Anne's building department is stricter than the standard IRC on fence work, expect fewer exemptions and more situations that require a permit. You're looking at roughly $27 – $82 in permit fees, plan on about 1 week for approval, plus you can apply online.

By Joey, Founder · Last verified March 29, 2026 · How we research →

Population: 3,616 Code: 2018 Verified: 2026-03-29 5 local rules

When you don’t need a Fence permit in Princess Anne

Exempt·Rule 1

Backyard fences 6 feet or under are exempt.

SourceMaryland Building Code / 2018 IRC
Exempt·Rule 2

Front yard fences 4 feet or under are exempt.

SourceMaryland Building Code / 2018 IRC

When you need a Fence permit in Princess Anne

Required·Rule 1

Pool barrier fencing requires a permit.

Estimated Fee$27 – $82
Typical Timelineabout 1 week
SourceMaryland Building Code / 2018 IRC
Required·Rule 2

Front yard fences over 4 feet require a permit.

Estimated Fee$27 – $82
Typical Timelineabout 1 week
SourceMaryland Building Code / 2018 IRC
Required·Rule 3

Fences over 6 feet require a permit.

Estimated Fee$27 – $82
Typical Timelineabout 1 week
SourceMaryland Building Code / 2018 IRC

Fence Permit Costs: Princess Anne vs. Nearby

Princess Anne comes in on the low side for Maryland. You're looking at $27 – $82 here, compared to the state average of $48 – $168.

CityEstimated Fee
Princess Anne $27 – $82
Baltimore $50 – $200
Columbia $45 – $180
Germantown $50 – $150

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Princess Anne permit costs →

Zoning Considerations

Zoning

Front-yard fences and fences above certain heights may require zoning approval. Many cities limit front-yard fence height to 3–4 feet. Check setback and height limits with your planning department.

Estimated Project Timeline in Princess Anne

Here's a typical timeline for a fence project in Princess Anne, MD:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Princess Anne's building department, apply online here.
Week 4
Plan review & approval
Typical processing time in Princess Anne: about 1 week. Plan review examiner checks drawings for code compliance.
Week 5+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Princess Anne's typical about 1 week permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Fence permit in Princess Anne, MD?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameSomerset County Permits
Address11916 Somerset Ave, Princess Anne, MD 21853
HoursMon-Fri 8am-4:30pm

Frequently Asked Questions

Estimated permit fees for Fence projects in Princess Anne, MD range from $27 – $82. Fees vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Fence projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Princess Anne can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Fence permits in Princess Anne is about 1 week. More complex projects may take longer if plan review is required.

Learn More About Fence Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Fence Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-03-29. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.