Concrete Slab Permit Requirements in Union, IL

Village of Union handles its own building permits (McHenry County only covers unincorporated areas, not incorporated villages). Building Inspector is available one hour per week, Tuesdays 3 PM to 4 PM. The village has not published its adopted residential code edition online; rules below use IRC 2021 as baseline (the most common adoption in the Chicago metro). No published fee schedule, no online application portal. Apply in person during Village Hall hours or email permits@unionillinois.org. Illinois state plumbing code (IDPH-licensed plumbers) and electrical licensing requirements apply regardless of local code adoption.

By Joey, Founder · Last verified April 18, 2026 · How we research →

Population: 600 Code: 2021 Verified: 2026-04-18 2 local rules

When you don’t need a Concrete Slab permit in Union

Exempt·Rule 1

A small concrete slab on grade (under 200 square feet, no structure on top) generally does not require a building permit in Union, IL under 2021 IRC R105.2 (sidewalks and similar). Verify with the Village Building Inspector at (815) 923-4153 (available Tuesdays 3 PM to 4 PM) before starting work.

Source2021 IRC baseline (Union has not published adopted code edition); Village of Union Building Inspector · view source

When you need a Concrete Slab permit in Union

Required·Rule 1

Larger concrete slabs (over 200 square feet) or any slab intended as a foundation for a future structure require a building permit in Union, IL under 2021 IRC R403. Verify with the Village Building Inspector at (815) 923-4153 (available Tuesdays 3 PM to 4 PM) before starting work.

Typical Timelineabout 2 weeks
Source2021 IRC baseline (Union has not published adopted code edition); Village of Union Building Inspector · view source

Concrete Slab Permit Costs: Union vs. Nearby

CityEstimated Fee
Union N/A
Chicago $75 – $600
Aurora $75 – $600
Joliet $75 – $600

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Union permit costs →

Zoning Considerations

Zoning

Concrete slabs contribute to impervious surface coverage. Austin, Portland, Seattle, and many coastal cities cap impervious cover at 40-65% of lot area. Sidewalks and curb cuts in the public right-of-way always require a separate Public Works encroachment permit.

Estimated Project Timeline in Union

Here's a typical timeline for a concrete slab project in Union, IL:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings.
Week 2
Submit permit application
Your contractor submits the application to Union's building department.
Week 3-4
Plan review & approval
Typical processing time in Union: about 2 weeks. Application review and permit issuance.
Week 5+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Union's typical about 2 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Concrete Slab permit in Union, IL?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameVillage of Union (Village Hall, Building Inspector)
Address17703 O'Cock Road, Union, IL 60180
HoursVillage Hall: Tue 10 AM to 4 PM, Thu 1 PM to 5 PM. Building Inspector available Tue 3 PM to 4 PM.

Frequently Asked Questions

Contact Union's building department for current Concrete Slab permit fee information. Fees typically vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Concrete Slab projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Union can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Concrete Slab permits in Union is about 2 weeks. More complex projects may take longer if plan review is required.

Learn More About Concrete Slab Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Concrete Slab Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-04-18. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.