Fence Permit Requirements in Centennial, CO

Centennial is a city of 106,883 residents in Colorado that follows the 2018 IRC. Centennial's building department is stricter than the standard IRC on fence work, expect fewer exemptions and more situations that require a permit. You're looking at roughly $45 – $180 in permit fees, plan on about 2 weeks for approval, plus you can apply online.

By Joey, Founder · Last verified March 29, 2026 · How we research →

Population: 106,883 Code: 2018 Verified: 2026-03-29 5 local rules

When you don’t need a Fence permit in Centennial

Exempt·Rule 1

Backyard fences 6 feet or under do not require a building permit.

SourceCity of Centennial Code / 2018 IRC
Exempt·Rule 2

Front yard fences 4 feet or under typically do not require a permit but must comply with zoning.

SourceCity of Centennial Code / 2018 IRC

When you need a Fence permit in Centennial

Required·Rule 1

Fences over 6 feet require a building permit.

Estimated Fee$45 – $180
Typical Timelineabout 2 weeks
SourceCity of Centennial Code / 2018 IRC
Required·Rule 2

Masonry/block fences require a building permit due to structural and footing requirements.

Estimated Fee$70 – $270
Typical Timelineabout 2 weeks
SourceCity of Centennial Code / 2018 IRC
Required·Rule 3

Pool barrier fences must meet safety requirements and typically require a permit.

Estimated Fee$45 – $180
Typical Timelineabout 1 week
SourceCity of Centennial Code / 2018 IRC

Fence Permit Costs: Centennial vs. Nearby

Centennial's fees are right in line with the Colorado average, $45 – $270 versus $48 – $166 statewide.

CityEstimated Fee
Centennial $45 – $270
Denver $75 – $250
Colorado Springs $50 – $200
Aurora $70 – $225

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Centennial permit costs →

Zoning & HOA Considerations

Zoning

Front-yard fences and fences above certain heights may require zoning approval. Many cities limit front-yard fence height to 3–4 feet. Check setback and height limits with your planning department.

HOA Communities

If you live in an HOA community: hOAs frequently restrict fence materials, colors, heights, and styles, often more strictly than city code. Review your CC&Rs and submit to your Architectural Review Committee (ARC) before applying for a city permit.

Estimated Project Timeline in Centennial

Here's a typical timeline for a fence project in Centennial, CO:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Centennial's building department, apply online here.
Week 4-5
Plan review & approval
Typical processing time in Centennial: about 2 weeks. Plan review examiner checks drawings for code compliance.
Week 6+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Centennial's typical about 2 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Fence permit in Centennial, CO?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameBuilding Division
Address13133 E. Arapahoe Rd., Centennial, CO 80112
HoursMon-Tue 8am-5pm; Wed 9am-5pm; Thu-Fri 8am-5pm

Frequently Asked Questions

Estimated permit fees for Fence projects in Centennial, CO range from $45 – $270. Fees vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Fence projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Centennial can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Fence permits in Centennial is about 2 weeks. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Fence Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Fence Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-03-29. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.