Shed Permit Requirements in Aurora, CO

Uses 2021 I-Codes with local amendments (Aurora Municipal Code Ch. 22). High altitude (5,471 ft), HVAC derating required. Spans Arapahoe, Adams, and Douglas counties. Aurora4Biz portal for permits. Flat-rate permits available for simple jobs. Email: permitcounter@auroragov.org

By Joey, Founder · Last verified March 29, 2026 · How we research →

Population: 386,261 Code: 2021 Verified: 2026-03-29 3 local rules

When you don’t need a Shed permit in Aurora

Exempt·Rule 1

Sheds 120 square feet or less without utilities are exempt.

SourceAurora Municipal Code Ch. 22 / 2021 I-Codes with local amendments

When you need a Shed permit in Aurora

Required·Rule 1

Sheds larger than 120 square feet require a building permit.

Estimated Fee$90 – $360
Typical Timelineabout 2 weeks
SourceAurora Municipal Code Ch. 22 / 2021 I-Codes with local amendments
Required·Rule 2

Sheds with electrical require permits.

Estimated Fee$135 – $450
Typical Timelineabout 2 weeks
SourceAurora Municipal Code Ch. 22 / 2021 I-Codes with local amendments

What Makes Aurora Different

Here's how Aurora's shed rules stack up against the standard IRC baseline that most of the country follows.

Stricter Than the IRC

Sheds larger than 120 square feet require a building permit in Aurora, CO.

Sheds with electrical require permits in Aurora, CO.

1 rule match the IRC baseline, no surprises there.

Shed Permit Costs: Aurora vs. Nearby

Aurora runs higher than average for Colorado. Expect $90 – $450 versus the state average of $66 – $235.

CityEstimated Fee
Aurora $90 – $450
Denver $100 – $500
Colorado Springs $50 – $300
Fort Collins $50 – $300

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Aurora permit costs →

Zoning & HOA Considerations

Zoning

Sheds may be subject to zoning setback requirements and lot coverage limits. Placement near property lines or in front yards may require zoning approval.

HOA Communities

If you live in an HOA community: many HOAs restrict or prohibit outbuildings. Check your CC&Rs for rules on shed size, placement, materials, and appearance before purchasing or building.

Estimated Project Timeline in Aurora

Here's a typical timeline for a shed project in Aurora, CO:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Aurora's building department, apply online here.
Week 4-5
Plan review & approval
Typical processing time in Aurora: about 2 weeks. Plan review examiner checks drawings for code compliance.
Week 6+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Aurora's typical about 2 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Shed permit in Aurora, CO?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameBuilding Division
Address15151 E. Alameda Pkwy., Suite 2400, Aurora, CO 80012
HoursMon/Tue/Thu/Fri 7:30am-4:30pm, Wed 8:30am-4:30pm

Frequently Asked Questions

Estimated permit fees for Shed projects in Aurora, CO range from $90 – $450. Fees vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Shed projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Aurora can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Shed permits in Aurora is about 2 weeks. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Shed Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Shed Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-03-29. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.