Fireplace / Wood Stove Permit Requirements in Aurora, CO

Uses 2021 I-Codes with local amendments (Aurora Municipal Code Ch. 22). High altitude (5,471 ft), HVAC derating required. Spans Arapahoe, Adams, and Douglas counties. Aurora4Biz portal for permits. Flat-rate permits available for simple jobs. Email: permitcounter@auroragov.org

By Joey, Founder · Last verified March 29, 2026 · How we research →

Population: 386,261 Code: 2021 Verified: 2026-03-29 4 local rules

When you don’t need a permit

Exempt·Rule 1

Installing a decorative vent-free gas log set into an existing masonry fireplace (with no new gas piping) is generally exempt from a permit under City of Aurora Building Code / 2021 IRC with Colorado Amendments. The gas shutoff must already exist at the hearth. Vent-free units must be listed per ANSI Z21.11.2 and not used in bedrooms.

SourceCity of Aurora Building Code / 2021 IRC with Colorado Amendments · view source

When you do need a permit

Required·Rule 1

Installing a new gas fireplace insert into an existing masonry opening (using existing gas line) requires a mechanical permit under City of Aurora Building Code / 2021 IRC with Colorado Amendments. The unit must be listed per ANSI Z21.50 and installed per manufacturer instructions. A gas pressure test is required.

Estimated Fee$150 – $420
Typical Timelineabout 2 weeks
SourceCity of Aurora Building Code / 2021 IRC with Colorado Amendments · view source
Required·Rule 2

New wood-burning fireplace construction requires both a building permit and a mechanical permit under City of Aurora Building Code / 2021 IRC with Colorado Amendments. Work must comply with IRC Chapter 10 (Chimneys and Fireplaces) including foundation, firebox, hearth, and chimney requirements. The 2-10-3 rule applies to chimney height.

Estimated Fee$300 – $600
Typical Timelineabout 3 weeks
SourceCity of Aurora Building Code / 2021 IRC with Colorado Amendments · view source
Required·Rule 3

Installing a gas fireplace with a new gas line extension requires building, mechanical, and plumbing permits under City of Aurora Building Code / 2021 IRC with Colorado Amendments. A licensed plumber must install the gas piping; a licensed HVAC/mechanical contractor must install the appliance. Separate inspections are required for gas piping and the final mechanical installation.

Estimated Fee$300 – $600
Typical Timelineabout 2 weeks
SourceCity of Aurora Building Code / 2021 IRC with Colorado Amendments · view source

Fireplace / Wood Stove Permit Costs: Aurora vs. Nearby

Aurora's fees are right in line with the Colorado average, $150 – $600 versus $133 – $476 statewide.

CityEstimated Fee
Aurora $150 – $600
Denver $75 – $800
Colorado Springs $75 – $800
Fort Collins $75 – $800

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Aurora permit costs →

Zoning & HOA Considerations

Zoning

Fireplace and wood stove installations rarely trigger zoning review. Many California air quality districts (SCAQMD, BAAQMD) prohibit NEW wood-burning fireplaces in new construction. Chimney height requirements must comply with IRC R1003.9 (3 ft above roof penetration, 2 ft above any point within 10 ft horizontally).

HOA Communities

If you live in an HOA community: hOAs in some communities prohibit wood-burning appliances entirely due to smoke and air quality concerns. Gas fireplaces are usually permitted. Chimney caps and exterior venting may face aesthetic review.

Estimated Project Timeline in Aurora

Here's a typical timeline for a fireplace / wood stove project in Aurora, CO:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Aurora's building department, apply online here.
Week 4-6
Plan review & approval
Typical processing time in Aurora: about 3 weeks. Plan review examiner checks drawings for code compliance.
Week 7+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Aurora's typical about 3 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Check your specific project

Answer a few quick questions to get a personalized answer for your exact project.

Check Now, Free →

Building Department Contact

NameBuilding Division
Address15151 E. Alameda Pkwy., Suite 2400, Aurora, CO 80012
HoursMon/Tue/Thu/Fri 7:30am-4:30pm, Wed 8:30am-4:30pm

Frequently Asked Questions

Estimated permit fees for Fireplace / Wood Stove projects in Aurora, CO range from $150 – $600. Fees vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Fireplace / Wood Stove projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Aurora can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Fireplace / Wood Stove permits in Aurora is about 2 weeks. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Fireplace / Wood Stove Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Fireplace / Wood Stove Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-03-29. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.