Demolition Permit Requirements in San Mateo County, CA

San Mateo County Planning and Building Department serves all UNINCORPORATED areas of San Mateo County, including the Midcoast communities of Montara (94037), Moss Beach (94038), El Granada (94018), Princeton, and Miramar. This record currently covers 94037 Montara only; other unincorporated Coastside ZIPs will be added in follow-up work. Incorporated cities (Daly City, San Mateo, Redwood City, Pacifica, Half Moon Bay, Belmont, Burlingame, Foster City, Menlo Park, etc.) run their own building departments — confirm parcel is unincorporated before applying here. CRITICAL Coastside overlay: all of 94037 is in the California Coastal Zone, so nearly any development (new structure, major addition, grading, demolition, some remodels) requires a Coastal Development Permit (CDP) from SMC Planning under the Midcoast Local Coastal Program (Midcoast LCP, approved by California Coastal Commission August 2012). Only narrow exemptions apply; appeals go to the Coastal Commission. California 2025 Building Standards Code (CRC/CBC/CFC) took effect statewide 2026-01-01; state code is enforceable regardless of whether the County has signed its local 2025 adoption ordinance (historical adoption was Ord. 4873 on 2022 cycle). Portions of Montara (upslope toward Montara Mountain / McNee Ranch) are in CAL FIRE Very High Fire Hazard Severity Zones; 2025 CRC Chapter 7A (ignition-resistant construction) applies. Seismic Design Category D; ultimate design wind ~110 mph. Parcels use septic (SMC Environmental Health Services, LAMP program) and private wells unless on Montara Water & Sanitary District (MWSD, 650-728-3358) sewer+water service. Online permits via Accela Citizen Access (ACA) at aca-prod.accela.com/smcgov. Fee schedules effective 2026-04-01. Building counter at 455 County Center, Redwood City.

By Joey, Founder · Last verified April 24, 2026 · How we research →

Population: 737,888 Code: 2025 CRC Verified: 2026-04-24 1 local rules

When you need a Demolition permit in San Mateo County

Required·Rule 1

94037), demolition of a structure requires a demolition permit AND Coastal Development Permit. Utility disconnects, asbestos survey (for pre-1978 structures triggering EPA NESHAP and Bay Area Air Quality Management District notification), and haul-off of debris required. CalRecycle construction-and-demolition debris recycling rules apply (50% diversion minimum).

Typical Timelineabout 6 weeks
SourceSMC Planning and Building / EPA NESHAP / BAAQMD / CalRecycle / Midcoast LCP · view source

Demolition Permit Costs: San Mateo County vs. Nearby

CityEstimated Fee
San Mateo County N/A
Los Angeles $150 – $1,500
Sacramento County $150 – $1,500
San Diego $150 – $1,500

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all San Mateo County permit costs →

Zoning & HOA Considerations

Zoning

Properties in historic districts may require historic review board approval before demolition. Some cities require a waiting period for demolition permits to allow for public comment.

HOA Communities

If you live in an HOA community: demolition of visible structures (garages, sheds, accessory buildings) may require HOA notification or approval. Check your CC&Rs, some communities require maintaining certain structures or replacing them within a set timeframe.

Estimated Project Timeline in San Mateo County

Here's a typical timeline for a demolition project in San Mateo County, CA:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings.
Week 2
Submit permit application
Your contractor submits the application to San Mateo County's building department, apply online here.
Week 3-9
Plan review & approval
Typical processing time in San Mateo County: about 6 weeks. Application review and permit issuance.
Week 10+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on San Mateo County's typical about 6 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Demolition permit in San Mateo County, CA?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameSan Mateo County Planning and Building Department
Address455 County Center, 2nd Floor, Redwood City, CA 94063
HoursMonday-Thursday 8:00 AM - 4:00 PM (closed noon-1 PM); closed Friday-Sunday

Frequently Asked Questions

Contact San Mateo County's building department for current Demolition permit fee information. Fees typically vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Demolition projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in San Mateo County can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Demolition permits in San Mateo County is about 6 weeks. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Demolition Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Demolition Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-04-24. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.