Permit history for 164 Summit Ave, Providence

Providence, RI · 43 permits on file · 2017–2019

43
Permits on file
2017
First permit
2019
Most recent
22
Unique contractors
$3,586,225
Declared value (all work)

Permits on file (43)

Ordered most recent first. Data from the city's open data portal.

Plumbing Permit
Install u/g grease waste; install 4 floor sinks; install 1 grease trap; tie onto existing plumbing system
Status: Active
Oct 22, 2019
Declared cost: $23,000
Sprinkler and Other Suppression Systems Permit Reconstruct
Relocation of sprinkler heads in renovation space
Status: Active
Sep 12, 2019
Declared cost: $5,500
Electrical Permit
Provide new access control wiring and fire alarm interconnection as needed at (8) door locations throughout the 22nd floor of miriam hospital.
Status: Complete
Feb 6, 2019
Declared cost: $123,074
Building Permit Modification to Existing
At rear loading dock area: replace 2 sidewalk panels with structural depth concrete panels, replace 2 existing oxygen tank pads with deeper (16") pads and additional reinforcement. addition of appx 9 36" (aff) bollards per state fire marsha
Contractor: J J CARDOSI INC
Status: Complete
Jan 17, 2019
Declared cost: $13,900
Sprinkler and Other Suppression Systems Permit Install
Relocate and add new sprinklers with an associated pipe connecting to the existing sprinkler system.
Status: Active
Jan 7, 2019
Declared cost: $4,000
Building Permit Modification to Existing
Install new and remove existing doors & partitions per plans
Status: Active
Dec 21, 2018
Declared cost: $40,000
Plumbing Permit
Copper pipe install approx. 1" x 120'. install k copper 1/2" x 40'. install 1" x 20' x-50 insulated
Contractor: TOMS PLUMBING LLC
Status: Active
Dec 14, 2018
Declared cost: $3,800
Electrical Permit Change/Revamp
Install underground electrical conduits to feed (3) new lighting bollards. wiring two glycol pumps and control wiring
Status: Active
Nov 20, 2018
Declared cost: $27,329
Electrical Permit
Installation of new transfer switch, raceways and wiring for new chiller. demolition of electrical for existing hvac items being deleted. minor power, lighting, fire alarm device and teledata outlet additions.
Contractor: ROSSI ELEC CO INC
Status: Active
Nov 7, 2018
Declared cost: $250,000
Electrical Permit
Install rigid conduit from existing location at oxygen takes to feed temporary oxygen skid. after demo of old tank area install new conduit and wiring for tank controls , lighting, and power.
Status: Complete
Oct 31, 2018
Declared cost: $12,000
Building Permit New Structure
Construct a 600 square foot steel building with insulated metal panel façade, to enclose a new chiller.
Status: Active
Aug 16, 2018
Declared cost: $542,882
Plumbing Permit
Install duplex sump pump
Status: Active
Aug 9, 2018
Declared cost: $37,000
Mechanical Permit Construct
Installing a snow melt system in the ambulatory area per plans and specs.
Status: Active
Jun 15, 2018
Declared cost: $74,866
Electrical Permit
Install (1) isolation panel, install all piping necessary to complete infrastructure for vir equipment, pipe and wire 200 amp feeder for ups, run voice and data lines, install new lighting
Status: Complete
Apr 23, 2018
Declared cost: $95,000
Building Permit Modification to Existing
Unistrut structure for new equipment and new finishes through out room
Status: Active
Apr 19, 2018
Declared cost: $80,000
Building Permit Modification to Existing
New flooring, acoustical ceiling, frame and drywall around duct work, add structural to floor below.
Status: Active
Apr 2, 2018
Declared cost: $75,585
Plumbing Permit
Medical gas only
Status: Complete
Mar 23, 2018
Declared cost: $18,000
Mechanical Permit Install
Furnish and install wet type sprinkler system and fdvc
Contractor: ENCORE HOLDINGS LLC
Status: Active
Feb 12, 2018
Declared cost: $11,000
Mechanical Permit Install
Hvac duct work for data closets on floors 1 - 4.
Status: Complete
Jan 18, 2018
Declared cost: $9,000
Electrical Permit
Annual permit for 2017
Status: Active
Jan 3, 2018
Declared cost: $160,000
Electrical Permit
Annual low voltage wiring maintenance permit for 2017
Status: Active
Jan 3, 2018
Declared cost: $38,676
Electrical Permit Change/Revamp
Install 1 800 amp docking station with main breaker
Status: Complete
Dec 6, 2017
Declared cost: $20,000
Electrical Permit New
The installation of a structured cabling system, which will support data and voice communications throughout the observation unit.
Contractor: SYNET, INCORPORATED
Status: Complete
Nov 29, 2017
Declared cost: $38,000
Building Permit Modification to Existing
Renovate existing administrative space into clinical observation cdu
Status: Complete
Nov 28, 2017
Declared cost: $432,515
Electrical Permit
Installation of new conduit, wire, wiring devices, lighting for 10 new observation rooms. rough piping only for nurse call installation by others is also included as well as revisions to automatic doors.
Status: Complete
Nov 28, 2017
Declared cost: $150,900
Plumbing Permit
Compfort plumbing & medical gas's for ten bed's & two bathrooms
Status: Active
Nov 27, 2017
Declared cost: $117,000
Electrical Permit
Relocate existing lighting and branch wiring to accommodate new hvac ductwork for data closets. provide branch circuit wiring for new fire dampers.
Status: Complete
Nov 15, 2017
Declared cost: $18,000
Electrical Permit
Provide new smoke duct detectors for smoke dampers.
Status: Complete
Nov 15, 2017
Declared cost: $5,300
Electrical Permit
Installation of new fire alarm smoke detectors and a/v units to provide coverage per drawings reviewed and approved by the r.i. state fire marshalls office.
Status: Complete
Nov 15, 2017
Declared cost: $14,100
Electrical Permit
Install cat6 cables for new cameras in the pharmacy
Status: Complete
Nov 3, 2017
Declared cost: $5,000
Mechanical Permit Install
Demo existing pipe. install new pipe for the vav's.
Status: Complete
Nov 1, 2017
Declared cost: $36,000
Plumbing Permit
Remove & replace around sixty feet of underground sanitary & kitchen waste piping.remove & replace five floor drains with floor sinks.install a sanitary vent for piping.
Status: Active
Oct 12, 2017
Declared cost: $18,000
Electrical Permit
Relocate one electrical panel 480v and add a single phase 120/240 panel to feed new fluorosopy equipment remove and relocate all existing lights and add 1 under counter fixtures
Status: Complete
Oct 5, 2017
Declared cost: $18,780
Mechanical Permit Replace (In-kind equipment)
Replace existing underground test header and fdc piping with new.
Status: Complete
Oct 5, 2017
Declared cost: $20,000
Building Permit Modification to Existing
Minor interior renovations and structural steel to support new medical equipment.
Status: Complete
Aug 30, 2017
Declared cost: $30,000
Plumbing Permit
Install one water closet; one lavatory and med gas outlets
Status: Active
Aug 22, 2017
Declared cost: $21,500
Building Permit Modification to Existing
Temporary breeching, stack modifications and additional elevated floor grating for access to boilers.
Status: Complete
Jul 31, 2017
Declared cost: $205,968
Electrical Permit New
Pipe and wire 2 electrical panels, install heat trace, make final connections to new air handler ahu 34
Status: Active
Jun 12, 2017
Declared cost: $15,000
Electrical Permit
Install wiring in mechanical room # 71 for 3 replacement air handler units . replace 21 light fixtures
Contractor: K ELECTRIC INC
Status: Complete
May 9, 2017
Declared cost: $62,800
Mechanical Permit Replace (In-kind equipment)
Replacing ahu 34 on rooftop
Status: Complete
Apr 6, 2017
Declared cost: $228,500
Electrical Permit
Disconnect existing chiller. run new line and wire in new chiller and vfd at miriam hospital
Status: Complete
Mar 8, 2017
Declared cost: $30,000
Electrical Permit
Install tele/data cabling to four new wall locations in the fire command center room
Status: Complete
Jan 27, 2017
Declared cost: $2,450
Building Permit Modification to Existing
Remove and replace existing rooftop mounted air handling unit. work to include the erection of structural steel equipment support and service platform.
Status: Complete
Jan 17, 2017
Declared cost: $451,800

Check permits at another Providence address

Free instant lookup, no signup.

Search Providence permits →
Disclaimer: Permit data comes from Providence's official open data portal. Records may be incomplete for older permits, and not every home-improvement project requires a permit. Verify with the Providence building department before buying, selling, or planning work.