Permit history for 800 28th St E
Minneapolis, MN · 117 permits on file · 2021–2026
117
Permits on file
2021
First permit
2026
Most recent
12
Unique contractors
$37,401,658
Declared value (all work)
Permits on file (117)
Ordered most recent first. Data from the city's open data portal.
Mechanical ComMFDNR
Installing chw crac unit mw crac 203,204,205,206,207,208,209. installing refrigeration crac units taf dxss 6m3b/3a per approved plans.
Contractor:
Harris St Paul Inc
Status: Issued
May 20, 2026
Declared cost: $340,933
Permit fee: $4,889
Mechanical ComMFDNR
I moved the symbol /abbreviation plan sheet m000 to the for-reverence file. (bldg 1171985 - projectdox prod ) chw crac unit mw crac 201/202. 4 a/c, 2 crac for level 3 and 4 a/c for it rooms and it closet. also duct modifications for level
Contractor:
Harris St Paul Inc
Status: Issued
May 14, 2026
Declared cost: $340,933
Permit fee: $4,889
Mechanical ComMFDNR
Add chw crac unit to b2, e3079, pb3667, h0229b, ck1843, ck2799, h3117, e87d6. add refrigeration crac unit to pb6600d, w7114e. add ahu to serve r1 data rm. provide and install miscellaneous duct, vavs, grds, chw and refrigeration pipin
Contractor:
Harris St Paul Inc
Status: Issued
Apr 28, 2026
Declared cost: $1,196,000
Permit fee: $16,242
Plumbing ComMaj
Waste and vent work at abbott northwestern hospital. this project is for a state licensed health care facility and the plumbing plan review has been completed by the minnesota department of labor and industry in lieu of a review by th
Contractor:
Harris St Paul Inc
Status: Issued
Apr 7, 2026
Permit fee: $125
Commercial RoofWind
Reroof -acw certificate of occupancy required no special inspections required no 2020 msbc
Contractor:
PETERSON BROTHERS ROOFING AND CONSTRUCTION INC
Status: Issued
Feb 24, 2026
Declared cost: $3,200,000
Permit fee: $21,851
Commercial Remodel
Updating the abbott northwestern taf and main hospital west building data closets with new technology on 2nd and 3rd floor. work includes electrical and hvac (rooms 2903m, 2905m, and w2701). this work is related to projects bldg1143753, bld
Contractor:
M . A . MORTENSON
Status: Issued
Feb 11, 2026
Declared cost: $552,321
Permit fee: $8,866
Commercial Remodel
Abbott northwestern piper building and main east building data closet upgrades. work to be done on 2nd, 3rd, 6th floor. see pages "level 02 life safety plan", "level 03 life safety plan", and "level 06 life safety plan" for data closet
Contractor:
M . A . MORTENSON
Status: Issued
Feb 3, 2026
Declared cost: $920,536
Permit fee: $13,240
Mechanical ComMFDNR
Duct alterations to data room k2 through k8. adding 2 owner crac units.
Contractor:
Harris St Paul Inc
Status: Issued
Jan 28, 2026
Declared cost: $16,000
Permit fee: $326
Jan 27, 2026
Declared cost: $16,000
Permit fee: $326
Commercial Remodel
In existing hospital, update data closets on ll, 1st, 2nd, and 7th floors (rooms g928a, ck1842, ck2799 h0229, w7114g). this work is related to projects bldg1143753 and bldg1155448 -acw certificate of occupancy required no special in
Contractor:
M . A . MORTENSON
Status: Issued
Jan 8, 2026
Declared cost: $920,535
Permit fee: $13,240
Plumbing ComMin
Abbott northwestern 5th floor replace one water fountain and demolishing 4 sinks (and capping water lines) in office area of 5th floor.
Contractor:
Harris St Paul Inc
Status: Closed
Jan 6, 2026
Permit fee: $249
Dec 17, 2025
Permit fee: $1,243
Plumbing ComMin
Install waste stand pipe and rpz water line for new bone saw. total job valuation: $20,100.00.
Contractor:
Harris St Paul Inc
Status: Closed
Dec 5, 2025
Permit fee: $85
Commercial Remodel
Update heart hospital data closets certificate of occupancy required: no special inspections required: no separate permits are required for electrical, plumbing, and heating/air conditioning/ventilation work. occupancy: b/i-2
Contractor:
MORTENSON CONSTRUCTION
Status: Issued
Nov 3, 2025
Declared cost: $1,031,000
Permit fee: $8,977
Mechanical ComMFDNR
Replace existing boilers with new ahu in mechanical room. remodel mri-d with added piping, ductwork, accessories and equipment. bldg1138373 new ducts and piping though out building including roof.
Contractor:
Harris St Paul Inc
Status: Issued
Nov 3, 2025
Declared cost: $500,000
Permit fee: $7,005
Mechanical ComMFDNR
Rework ductwork in ed ct and mechanical equipment room. replace vav and add chilled water station with heat exchanger, pump and associated accessories per plans
Contractor:
Harris St Paul Inc
Status: Issued
Sep 18, 2025
Declared cost: $120,000
Permit fee: $1,951
Sep 17, 2025
Declared cost: $16,500
Permit fee: $337
Plumbing ComMin
Demo sink, install new faucet and sink
Contractor:
Harris St Paul Inc
Status: Closed
Aug 28, 2025
Permit fee: $85
Aug 28, 2025
Permit fee: $85
Plumbing ComMin
Install new domestic water to mri-d expansion, along with (3) lavs and (1) mop-sink.
Contractor:
Harris St Paul Inc
Status: Closed
Aug 28, 2025
Permit fee: $167
Mechanical ComMFDNR
" controls are not included in this permit. the controls contractor shall obtain a separate permit. " hvac system, installing vav boxes with hot water reheat coils, grds and all associated ductwork per approved plans.
Contractor:
Harris St Paul Inc
Status: Issued
Aug 7, 2025
Declared cost: $164,800
Permit fee: $2,547
Commercial Remodel
Remodel of ct room e1612 for new equipment. certificate of occupancy required no const type: 1a occupancy: i2 2020 msbc sprinklered: yes architect: leo daly engineer: mbj
Contractor:
MORTENSON CONSTRUCTION
Status: Issued
Jul 31, 2025
Declared cost: $370,000
Permit fee: $6,370
Plumbing ComMin
Abbott west. restrooms & drinking fountain
Contractor:
Harris St Paul Inc
Status: Closed
Jul 3, 2025
Permit fee: $415
Commercial Remodel
Alterations to replace emergency department ct machine and associated equipment. certificate of occupancy required no const type: 1a occupancy: i2 2020 msbc sprinklered: yes architect: nelson #42247 leo da
Contractor:
JE DUNN CONSTRUCTION
Status: Closed
Jun 27, 2025
Declared cost: $935,119
Permit fee: $13,418
Commercial Remodel
Remodeling outpatient clinic areas of 3rd and 6th floor. piper neuro expansion. certificate of occupancy required no const type: 1a occupancy: b - outpatient clinic space 2020 msbc sprinklered: yes architect
Contractor:
JE DUNN CONSTRUCTION
Status: Closed
May 29, 2025
Declared cost: $2,913,460
Permit fee: $32,539
Commercial Remodel
Remodel on 1st floor for equipment const type: ii-b occupancy: i-2 2020 msbc architect: 53825 - abeln, daniel jonathon @ eapc engineer: 23148 - trofimova-peterson, irene @ mbj
Contractor:
JE DUNN CONSTRUCTION
Status: Closed
May 29, 2025
Declared cost: $4,850,028
Permit fee: $50,748
Mechanical ComMFDNR
Bldg1111397 3 new data center cooling systems. data rooms are located on level 2,3, and 4 ducted fan coils units. condensers are located on the roof.
Contractor:
Harris St Paul Inc
Status: Closed
Apr 17, 2025
Declared cost: $243,000
Permit fee: $3,587
Commercial Remodel
Alterations related to equipment upgrades for winter cooling. engineer: trofimova-peterson #23148
Contractor:
JE DUNN CONSTRUCTION
Status: Closed
Mar 25, 2025
Declared cost: $3,762,516
Permit fee: $32,839
Mar 17, 2025
Declared cost: $6,800
Permit fee: $139
Plumbing ComMin
Demo (1) existing sink. provide and install (1) new sink faucet and trim for integral sink.
Contractor:
Harris St Paul Inc
Status: Closed
Mar 6, 2025
Permit fee: $85
Mechanical ComMFDNR
Replacing grds
and all associated ductwork per approved plans.
Contractor:
Harris St Paul Inc
Status: Issued
Mar 4, 2025
Declared cost: $2,000
Permit fee: $85
Commercial Remodel
Remodel x-ray room c. certificate of occupancy required no const type: 1a occupancy: i2 2020 msbc architect: daly
Contractor:
JE DUNN CONSTRUCTION
Status: Closed
Feb 5, 2025
Declared cost: $285,905
Permit fee: $5,164
Mechanical ComMFDNR
Installing two vav boxes, grds
and all associated ductwork per approved plans.
Contractor:
Harris St Paul Inc
Status: Issued
Jan 29, 2025
Declared cost: $24,880
Permit fee: $508
Jan 28, 2025
Permit fee: $85
Plumbing ComMin
1st and 2nd flr nuc med and uptake - scope of work: demo (1) mop sink and (1) ss drop in counter sink. provide and install (1) mop sink and (1) ss drop in counter sink.fixture counts are: (1) mop sink.(1) ss drop in hand sink
Contractor:
Harris St Paul Inc
Status: Closed
Dec 13, 2024
Permit fee: $85
Mechanical ComMFDNR
. the specific area of work was not identified in the
construction documents.
Contractor:
Harris St Paul Inc
Status: Closed
Nov 21, 2024
Declared cost: $80,850
Permit fee: $1,430
Plumbing ComMin
Provide and install (1) ro/ di system. connect water and waste to existing services. install(1) floor drain. (1) mop sink.
Contractor:
Harris St Paul Inc
Status: Closed
Nov 12, 2024
Permit fee: $167
Commercial Remodel
Remodel nuclear medicine and uptake area on 2nd floor heart hospital building. certificate of occupancy required no const type: 1a occupancy: i2 2020 msbc sprinklered: yes architect: johansen #53808
Contractor:
JE DUNN CONSTRUCTION
Status: Issued
Oct 7, 2024
Declared cost: $692,032
Permit fee: $10,530
Commercial Remodel
Replace existing side hinged doors with new sliding glass doors and 90 minute rated overhead coiling door per drawings, the doors being replaced are not a required part of the means of egress for either building. certificate of occupancy
Contractor:
JE DUNN CONSTRUCTION
Status: Closed
Oct 7, 2024
Declared cost: $143,000
Permit fee: $3,110
Mechanical TempHeat
(11) temporary gas heaters will be installed at abbott northwestern surgical and critical care building, connecting to holmes heart hospital and the taf building. the lower-level through level 10 will be heated with the (11) gas heaters, al
Contractor:
Harris St Paul Inc
Status: Closed
Oct 3, 2024
Permit fee: $807
Commercial Remodel
Update mri-c rooms e 1897 and e 1892 for new exablate equipment on level 1 of the main hospital certificate of occupancy required: no special inspections required: no separate permits are required for electrical, plumbing, and he
Contractor:
MORTENSON CONSTRUCTION
Status: Closed
Sep 20, 2024
Declared cost: $275,000
Permit fee: $5,006
Mechanical ComMFDNR
Installing 5 fire/smoke dampers in new central heating plant basement tunnel. plans uploaded. bldg1058241
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Issued
May 24, 2024
Declared cost: $11,200
Permit fee: $228
Mechanical ComMFDRR
Abbott northwestern hospital - piper building ahu repairs/upgrades. replace supply fans, return fans, cooling coils, and humidifiers in (3) existing air handling units. lower level piper s-3, ground level piper s-1, 2nd floor piper s-7.
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
May 2, 2024
Declared cost: $657,500
Permit fee: $9,100
Commercial RoofWind
Flat roof - epdm general requirements for flat roof replacements. the roof covering is to meet the minnesota building code performance requirements of section 1504, the fire classification of section 1505 and the material requirements as
Contractor:
PETERSON BROTHERS ROOFING
Status: Expired
Mar 8, 2024
Declared cost: $700,000
Permit fee: $6,571
Plumbing ComMin
Relocate one existing sink in existing xray room
Contractor:
Harris St Paul Inc
Status: Closed
Mar 7, 2024
Permit fee: $85
Mechanical ComMFDRR
Modify existing return ductwork in xray room and change eggcrate size in one location
Contractor:
Harris St Paul Inc
Status: Closed
Mar 5, 2024
Declared cost: $4,674
Permit fee: $95
Mechanical ComMFDNR
Demoing and re-routing equipment, duct, and piping in demolition zone per approved plans. this permit is just for temporary demolition, contractor shall obtain mechanical permit for future remodeling.
Contractor:
Harris St Paul Inc
Status: Closed
Oct 17, 2023
Declared cost: $65,000
Permit fee: $1,220
Commercial RoofWind
Comercial roof replacement. (jjl) engineer to review window washing anchors.
Contractor:
PETERSON BROTHERS ROOFING
Status: Issued
Sep 22, 2023
Declared cost: $800,000
Permit fee: $7,311
Commercial Remodel
Demo - heart hospital main lobby area levels 1, 2, & 3 certificate of occupancy required: no special inspections required: no const type: 1-a occupancy: i-2 2020 msbc occupant load: tbd sprinklered:
Contractor:
MORTENSON
Status: Closed
Sep 12, 2023
Declared cost: $500,000
Permit fee: $8,237
Commercial New
Selective demolition and construction of valet hut and connections to existing parking helix certificate of occupancy required: no special inspections required: yes const type: 2-b occupancy: b 2020 msbc o
Contractor:
MORTENSON
Status: Closed
Aug 22, 2023
Declared cost: $1,500,000
Permit fee: $18,999
Mechanical ComMFDNR
Modify duct for new floor plan. plans are available.
Contractor:
Harris St Paul Inc
Status: Closed
Aug 18, 2023
Declared cost: $24,000
Permit fee: $490
Mechanical ComMFDNR
Minor duct alterations. plans available. level 2 h2171 c5 command center
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
Aug 11, 2023
Declared cost: $3,100
Permit fee: $86
Plumbing FoodBev
Add (1) drop-in sink. add (1) plumbed connection for owner provided coffee machine plan review is done by doli, not mpls, no mpls plumbing plan review required.2023-08-08 - lea
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
Aug 10, 2023
Permit fee: $85
Plumbing ComMin
For parking ramps 1 and 3 at 880 28th st e - reroute parking ramp 3 stairwell drains, and one roof drain out of ramp 1. ramp 1 is being demolished.
Contractor:
Harris St Paul Inc
Status: Closed
Jul 6, 2023
Permit fee: $249
Mechanical ComMFDNR
Lab hood modification per attached plans.
Contractor:
Harris St Paul Inc
Status: Closed
Jun 20, 2023
Declared cost: $2,468
Permit fee: $85
Plumbing ComMin
2nd floor histology lab upgrade- new restroom sink
Contractor:
Harris St Paul Inc
Status: Closed
Jun 13, 2023
Permit fee: $85
Commercial Remodel
Remodel lower level courage kenny building for office space associated with bldg982846 certificate of occupancy required: no const type: 1-b occupancy: b 2020 msbc occupant load: 60 sprinklered: yes
Contractor:
MORTENSON
Status: Issued
Jun 6, 2023
Declared cost: $500,000
Permit fee: $8,237
Plumbing ComMin
Break room sink in new lower level office of courage kenny building
Contractor:
Harris St Paul Inc
Status: Closed
Apr 25, 2023
Permit fee: $85
Plumbing ComMin
Installation of storm drainage for hospital skyway
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
Apr 17, 2023
Permit fee: $581
Mechanical ComMFDNR
1. shall install co2 sensors as specified. alteration of hvac system, reusing existing system to support the new layout. installing grds and all associated ductwork. refer to
attached drawings.
Contractor:
Harris St Paul Inc
Status: Closed
Apr 5, 2023
Declared cost: $24,000
Permit fee: $490
Commercial Remodel
Interior remodel certificate of occupancy required: no special inspections required: no const type: 1a occupancy: i-2 2020 msbc sprinklered: yes architect: thomas beck #46352
Contractor:
MORTENSON
Status: Closed
Mar 13, 2023
Declared cost: $15,000
Permit fee: $621
Commercial Remodel
Remodel lower level courage kenny building for office space certificate of occupancy required: no const type: 1-b occupancy: b 2020 msbc occupant load: 45 sprinklered: yes
Contractor:
MORTENSON
Status: Closed
Mar 7, 2023
Declared cost: $330,000
Permit fee: $5,796
Mechanical ComMFDNR
Skyway hvac system, installing 4 packaged units with dx coil and gas heat, vrf system with 8 fan-coil units and 3 vrf condensing units, cooling only split system, electric unit heater, grds
and all associated ductwork. refer to attached dra
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
Feb 13, 2023
Declared cost: $411,298
Permit fee: $5,825
Jan 12, 2023
Permit fee: $167
Plumbing FoodBev
Renovation to the tenth avenue facility restrooms on the mezzanine level of 3rd and 4th floors. including mens and womens restroom, replacement of all fixtures and floor drains.
Contractor:
Harris St Paul Inc
Status: Closed
Dec 27, 2022
Permit fee: $1,307
Mechanical ComMFDNR
Rework of exhaust systems on level 3 and 4. existing life safety damper and ducts for electrical room exhaust to be re-used , new electrical room exhaust fan only. alternate 1 in note two wasn't exercised. plans attached.
Contractor:
Harris St Paul Inc
Status: Closed
Dec 20, 2022
Declared cost: $155,682
Permit fee: $2,426
Mechanical ComMFDNR
Drawings attached. complete snow melt system per design. also conditioning new entrance/lobby area. 2 chu west vesibule and ck vestibule.
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
Dec 20, 2022
Declared cost: $175,813
Permit fee: $2,693
Plumbing ComMin
Replace (1) existing sink with new using existing rough plumbing. add plumbed coffee machine using existing sink rough plumbing.
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
Dec 19, 2022
Permit fee: $85
Plumbing ComMin
Reinstall wastelines accomodate new drive lane
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
Dec 12, 2022
Permit fee: $125
Mechanical ComMFDNR
Repiping gas for generator rtu and skyway due to meter moves. also new 3" gas for n2 new boilers. plans attached.
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
Dec 9, 2022
Declared cost: $279,375
Permit fee: $4,653
Dec 2, 2022
Permit fee: $441
Commercial Remodel
(dmh-projectdox) select demo at west main floor entry and common area . demo select partition walls for future remodel. separate application, plans, permits and approvals required for remodeling. removal of escalator and equipment
Contractor:
MORTENSON
Status: Closed
Nov 18, 2022
Declared cost: $100,000
Permit fee: $2,493
Mechanical ComMFDNR
In neuro room replacing existing fan coil unit adding one cooling
only vav box, grds and all associated ductworks. refer to attached drawings.
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
Nov 10, 2022
Declared cost: $24,051
Permit fee: $491
Commercial Remodel
Convert room 1294 into temporary pop up cafeteria , take out no seating (maa) const type: ii occupancy: b 2020 msbc occupant load: 20 sprinklered:yes 20% accessibility upgrades____fully______ tenant: abbot nor
Contractor:
M . A . MORTENSON
Status: Closed
Nov 7, 2022
Declared cost: $275,000
Permit fee: $7,491
Plumbing FoodBev
Modifying existing doctors lounge with new food service project is at a hospital doli to review plumbing. no minneapolis plumbing plant review.
Contractor:
Harris St Paul Inc
Status: Closed
Oct 27, 2022
Permit fee: $125
Commercial Remodel
Concrete and post tension repairs level 3. (jjl) engineer: mbj engineers - dan murphy #13373 special inspections: see sheet s001
Contractor:
Cy-Con, Inc.
Status: Expired
Sep 15, 2022
Declared cost: $247,657
Permit fee: $4,618
Plumbing ComFdBv
Installation of new anti ligature fixtures
Contractor:
Harris St Paul Inc
Status: Closed
Aug 18, 2022
Permit fee: $125
Mechanical ComMFDNR
Modification of supply duct, exhaust duct, and new grd installation. refer to attached drawings.
Contractor:
Harris St Paul Inc
Status: Closed
Aug 11, 2022
Declared cost: $22,117
Permit fee: $451
Commercial Remodel
Remodel 4 existing seclusion room areas on 3rd and 4th floor - courage kenny medical building. certificate of occupancy required: no const type: 1b occupancy: b 2020 msbc sprinklered: yes tenant: abbott
Contractor:
M . A . MORTENSON
Status: Closed
Jul 18, 2022
Declared cost: $580,000
Permit fee: $9,188
Mechanical ComMFDNR
Adding three vav boxes with reheat coil, relocating existing vav boxes, grds and all associated ductwork. refer to attached drawings.
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
Jul 6, 2022
Declared cost: $42,879
Permit fee: $875
Mechanical ComMFDNR
Hvac system, installing new fan-powered box with hot water heating, split dx cooling system include indoor fan-coil and outdoor condensing unit, condensate pump, hydronic piping, grds and all associated ductwork. refer to attached drawings.
Contractor:
Harris St Paul Inc
Status: Closed
Jun 22, 2022
Declared cost: $53,000
Permit fee: $1,060
Mechanical ComMFDNR
Ductwork modification and diffuser installation per attached drawings.
Contractor:
Harris St Paul Inc
Status: Closed
Jun 16, 2022
Declared cost: $9,651
Permit fee: $197
Mechanical ComMFDNR
Modifying breakroom duct work, low pressure steam piping, grds and all associated ductwork. refer to attached drawings.
Contractor:
Harris St Paul Inc
Status: Closed
Jun 3, 2022
Declared cost: $35,560
Permit fee: $725
Plumbing ComFdBv
Install 2 break room sinks, floor drains, clean out and ice maker. reconnect 2 owner provided washers and owner provided 3 comp sink.
Contractor:
Harris St Paul Inc
Status: Closed
Jun 2, 2022
Permit fee: $208
Commercial Remodel
Interior remodel of existing endoscopy room on 5th floor at abbott northwestern hospital. no structural work. (jjl) some work on the floor under bldg908871. certificate of occupancy required no special inspections required no
Contractor:
JE DUNN CONSTRUCTION
Status: Closed
May 30, 2022
Declared cost: $130,000
Permit fee: $2,924
Commercial Remodel
Lower level remodel of quick turn room and staff break lounge. certificate of occupancy required: no const type: 1a occupancy: i2 2020 msbc sprinklered: yes architect: nelson
Contractor:
J.E. Dunn Construction Company
Status: Closed
May 27, 2022
Declared cost: $660,000
Permit fee: $10,138
Plumbing ComFdBv
Direct replacement of existing waste piping in piper bldg canopy area. no fixtures
Contractor:
Harris St Paul Inc
Status: Closed
May 20, 2022
Permit fee: $249
Commercial Remodel
Replace defs (direct-applied exterior finish system) soffit and leaking and damaged piping provide non-combustible framing, batt insulation (not foam plastic), and densglass fireguard sheathing as detailed. new or disrupted penetrations o
Contractor:
J.E. Dunn Construction Company
Status: Closed
May 2, 2022
Declared cost: $667,878
Permit fee: $8,284
Commercial Remodel
Abbott northwest hospital security upgrades required egress doors shall be readily openable from the egress side without the use of a key or special knowledge or effort or shall comply w/ msbc section 1010.1.9.7. certificate of occupancy
Contractor:
M.A. MORTENSON
Status: Closed
Apr 28, 2022
Declared cost: $172,200
Permit fee: $3,541
Commercial Remodel
Minor security upgrades - mainly card readers and cameras.
Contractor:
M.A. MORTENSON
Status: Closed
Apr 1, 2022
Declared cost: $6,000
Permit fee: $311
Mechanical ComMFDNR
Hvac system for wide open shell area for simulation lab, conference center and board room, installing 25000 cfm air handling unit, two exhaust fans, electric humidifier, 28 vav boxes, exhaust hood, grds and all associated ductwork. refer to
Contractor:
Harris St Paul Inc
Status: Closed
Mar 14, 2022
Declared cost: $456,363
Permit fee: $6,425
Mechanical ComMFDNR
Alteration for new bike center, adding 4100 cfm air handling unit, two rooftop units, one heat pump, eight electric unit heaters, eleven vav boxes, air curtain, grds
and all associated ductwork. refer to attached drawings.
Contractor:
Harris St Paul Inc
Status: Closed
Mar 7, 2022
Declared cost: $387,653
Permit fee: $5,584
Mechanical ComMFDNR
Adding two supply duct and diffusers, exhaust duct , two fire dampers and associated per attached plan.
Contractor:
Harris St Paul Inc
Status: Closed
Feb 28, 2022
Declared cost: $3,267
Permit fee: $86
Commercial Remodel
Minor alterations on 3rd floor - relocation of pei pharmacy. certificate of occupancy required no const type: 1a occupancy: i1 2020 msbc sprinklered: yes tenant: anw floor(s): 3rd
Contractor:
JE DUNN CONSTRUCTION
Status: Closed
Feb 18, 2022
Declared cost: $68,000
Permit fee: $1,917
Mechanical ComMFDRR
Replacing an existing chiller with 56 tons air cooled chiller adding heat exchanger, supply and return chilled water pipes, replacing one pump. refer to attached drawings.
Contractor:
Harris St Paul Inc
Status: Closed
Feb 14, 2022
Declared cost: $185,125
Permit fee: $2,817
Plumbing ComFdBv
Restroom & breakroom fixtures for new simulation lab+conference ctr+board rm addition
Contractor:
Harris St Paul Inc
Status: Closed
Feb 10, 2022
Permit fee: $1,574
Plumbing ComFdBv
Fixtures for new bike center on 10th ave side of campus
Contractor:
Harris St Paul Inc
Status: Closed
Feb 10, 2022
Permit fee: $1,431
Commercial Remodel
Lower level surgery area - phase i remodeling certificate of occupancy required no special inspections required no const type: i-a occupancy: i-2 2020 msbc occupant load: no change sprinklered: yes architect:
Contractor:
JE DUNN CONSTRUCTION
Status: Closed
Feb 1, 2022
Declared cost: $941,354
Permit fee: $13,490
Commercial Remodel
(dmh - projectdox) remodel/ updates to 988 sqft. reception and waiting area, and 1 exam room at main floor level. rooms ck1750, ck1751 & ck1766. const type: i occupancy: b 2020 msbc sprinkled: yes 20% accessibility upgra
Contractor:
MORTENSON CONSTRUCTION
Status: Closed
Jan 27, 2022
Declared cost: $106,000
Permit fee: $2,579
Mechanical ComMFDNR
This permit is companion of permit bldg912815, adding smoke damper and duct per attached plan.
Contractor:
Harris St Paul Inc
Status: Closed
Dec 23, 2021
Declared cost: $3,550
Permit fee: $86
Mechanical ComMFDNR
This permit is companion of bldg894021, the scope of work for this permit is just sheet metal rough-in for the storefront area of ramp 7. refer to attached drawings.
Contractor:
Go Fetsch Mechanical LLC
Status: Closed
Dec 23, 2021
Declared cost: $46,533
Permit fee: $949
Mechanical ComMFDNR
Hvac renovation for bronchoscopy area, replacing one vav box with hydronic coil and exhaust fan, adding grd's and all associated ductwork. refer to attached drawings.
Contractor:
Harris St Paul Inc
Status: Closed
Nov 8, 2021
Declared cost: $28,250
Permit fee: $576
Commercial Remodel
Repair structural component - concrete columns at 2 locations in parking garage ----- engineer: daniel e murphy - 13373 occupancy: s-2 construction type: i-b sprinklered: no ----- issuance of this permit shall not be construed as al
Contractor:
Cy-Con, Inc.
Status: Closed
Oct 28, 2021
Declared cost: $36,378
Permit fee: $1,267
Plumbing ComFdBv
For wasie building temporary offices on 1st floor - add 1 handwashing sink
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
Oct 26, 2021
Permit fee: $85
Mechanical TempHeat
Temporary heaters - provide temp service heat for a new and existing parking garage under construction at abbott northwest. gas pipeline to be
installed and service 10 temp heaters (hi-lo df heaters).
each heater can consume up to 1,500 c
Contractor:
Harris St Paul Inc
Status: Closed
Oct 21, 2021
Permit fee: $734
Plumbing ComFdBv
For piper building's bronchoscopy room - replace and relocate sink
Contractor:
Harris St Paul Inc
Status: Closed
Oct 21, 2021
Permit fee: $85
Commercial Remodel
Interior remodel of bronchoscopy room (rm 8) certificate of occupancy required: no special inspections required: no const type: 1a occupancy: b 2020 msbc sprinklered: yes architect: michael nelson #42247
Contractor:
JE DUNN CONSTRUCTION
Status: Closed
Oct 15, 2021
Declared cost: $340,000
Permit fee: $5,939
Mechanical ComMFDRR
Replacement with 2 new boilers - each over 400k btuh
Contractor:
Harris St Paul Inc
Status: Closed
Sep 27, 2021
Declared cost: $94,800
Permit fee: $2,198
Mechanical ComMFDNR
Hvac system for temporary construction office, modifying existing ductwork per new layout. refer to attached drawings.
Contractor:
Metropolitan Mechanical Contractors Inc
Status: Closed
Sep 23, 2021
Declared cost: $34,300
Permit fee: $700
Mechanical ComMFDNR
Hvac system for 3 story addition to existing ramp and new ramp adding 4 air handling unit, 4 vav boxes, electric heaters, six exhaust fans, supply fan. twelve ductless split cooling system, grds and all associated ductwork. refer to attache
Contractor:
Harris St Paul Inc
Status: Closed
Aug 26, 2021
Declared cost: $671,704
Permit fee: $9,289
Commercial Remodel
Infill indoor pool in wasie building and remodel for temporary offices certificate of occupancy required: no special inspections required: no sprinklered: no architect: none engineer:
Contractor:
JE DUNN CONSTRUCTION
Status: Closed
Aug 6, 2021
Declared cost: $97,524
Permit fee: $2,457
Plumbing ComNoFdBv
Furnish and install plumbing scope for abbott nw transportation hub project. scope includes: expansion to parking ramp 6 and construction of new parking ramp 7 at abbott nw hospital. ramp 6 is adding 2 levels and ramp 7 is 8 levels.
Contractor:
Harris St Paul Inc
Status: Closed
May 27, 2021
Permit fee: $6,669
Commercial Remodel
Replace large/heavy machine/equipment, renovate room including machine supports & room finishes - exisitng medical procedure room ----- 2020 minnesota state building code architect: peter g smith, 20095 engineer: mark cackoski, 25835 occupa
Contractor:
JE DUNN CONSTRUCTION
Status: Closed
May 10, 2021
Declared cost: $700,000
Permit fee: $10,614
Mechanical ComMFDNR
Adding a vav box and two air dampers, dx split system, hot water piping to vav box coil, duct work modification, supply diffusers and return grilles per attached drawings.
Contractor:
Harris St Paul Inc
Status: Closed
May 3, 2021
Declared cost: $65,000
Permit fee: $1,220
Plumbing ComNoFdBv
Install 1 new auxiliary drain outlet box. new medgas and waste piping. project happening on 3rd floor at anw main hospital for ep-2 room.
Contractor:
Harris St Paul Inc
Status: Closed
Apr 29, 2021
Permit fee: $85
Mechanical ComMFDRR
Due to new construction on adjacent land, relocating three louvers and providing combination of fire and smoke dampers as shown on attached drawings.
Contractor:
Harris St Paul Inc
Status: Closed
Apr 26, 2021
Declared cost: $30,606
Permit fee: $624
Apr 22, 2021
Permit fee: $85
Check permits at another Minneapolis address
Free instant lookup, no signup.
Search Minneapolis permits →