Permits on file (41)
Ordered most recent first. Data from the city's open data portal.
Alteration I-2 308.4
Interior alterations (lower level -pharmacy clean rm.) as per documents.
(subject to field approval. separate permits are required for all trade works.
May 1, 2026
Alteration
Alterations to install a second generator to an existing system on level 1 per plans. subject to field approval, separate trade permits required.
Oct 28, 2025
Alter Revision
Revision of bld2024-00561 to show true scope of work & cost performed. subject to field approval.
exterior & interior alterations to the basement & 1st floor as per plans.
31,000 sf renovation of the vacated dialysis department space
Jul 27, 2025
Alter Revision I-2 308.4
Revision to bld2025-00879 to code per plans. (revision of bld2024-02576 to show true scope of work & cost per plans.) subject to field approval.
includes drawing set labelled hed construction issue #11, dt. 07/18/2025 and containing arch
Jul 24, 2025
Alter Revision
Revision of bld2024-02576 to show true scope of work & cost per plans. subject to field approval.
renovations/alterations (assembly area/1st floor) per provided plans.(subject to field approval.)
Jun 11, 2025
Alteration
Fire alarm alterations (replacing fire alarm devices on k10) as per plans. subject to field approval.
May 21, 2025
Alteration
Interior alterations to the 3rd floor procedure room e335 to code per plans. subject to field approval. separate trade permits required.
May 8, 2025
Alteration I-2 308.4
Interior alterations on the 3rd flr as per plans. subject to field approval.
Apr 28, 2025
Alteration A-3
Exterior/interior alterations to k building as per plans.
installing new mechanical equipment for 3 procedure rooms. also installing roof mounted steel to support the new ahu that was server the 3 procedure rooms
Feb 25, 2025
Alteration A-3
Renovations/alterations (assembly area/1st floor) per provided plans.(subject to field approval.)
Feb 14, 2025
Alteration I-2 308.4
Removal and replacement of existing 4th floor mri & associated equipment to code per plans. subject to field approval.
Feb 10, 2025
New
Modifications to fire alarm system (cath lab) per provided plans & documents. (subject to field approval.)
Jan 21, 2025
Alteration B-304.1
Modifications to fire alarm system (k bldg-10th floor) per provided plans & dpocuments. (subject to field approval.)
Dec 27, 2024
Alter Revision
Revise (bld2024-01635) to reflect true scpoe of work per plans.
(interior alterations/renovations (10th floor) per provided plans. (subject to field approval.)
Dec 23, 2024
Alteration A-3
Interior alterations in an existing auditorium to code per plans. subject to field approval. separate trade permits required.
Dec 16, 2024
Alteration I-2 308.4
Interior alterations (upgrade existing 3rd floor imaging equipment) per plans
(subject to field approval.)
renovation to
Dec 2, 2024
Alteration
Modifications to fire alarm system (lower level-pharmacy) per provided plans & documents. (subject to field approval.)
Oct 22, 2024
Alteration B-304.1
Interior renovations/alterations (10th floor) per provided plans. (subject to field approval.)
Oct 17, 2024
Alteration
Interior alteration to convert existing storage area to a cath lab on the 2nd floor per plans. subject to field approval.
Aug 26, 2024
Alteration
Modifications to fire alarm system (1st floor) per provided plans & documents. (subject to field approval.)
Jul 15, 2024
Alteration
Interior alterations to pharmacy stock room per plans. subject to field approval. separate trade permits required.
May 29, 2024
Alteration
Exterior & interior alterations to the basement & 1st floor as per plans.
31,000 sf renovation of the vacated dialysis department space on the 1st floor of the hfh west pavilion building for the new gastroenterology/endoscopy department.
May 17, 2024
Alteration B-304.1
Interior alterations at an existing restaurant (subway) per plans. subject to field approval, separate trade permits required.
Apr 30, 2024
Alteration
Removal of existing kitchen equipment and relocation of equipment previously installed at one ford place per plans. subject to field approval.
Mar 18, 2024
Alteration
Interior alterations (1st floor) per provided plans (subject to field approval.)
Feb 5, 2024
Alteration
Interior/exterior alterations as per plans. subject to all applicable federal, state & local executive orders.
Aug 26, 2023
Alteration
Install roof level guard rails at (stair 1 and service elevator areas per plans. (subject to field approval.)
Aug 22, 2023
Alteration
Fire alarm as per plans. subject to all applicable federal, state & local executive orders.
Apr 27, 2023
Alteration
Interior alterations of the 4th floor of the hfhs education and research building per plans. subject to field approval.
Jun 8, 2022
New
Upgrades to fire alarm system residents lounge(m-1) as per plans. subject to all applicable federal, state & local executive orders.
Apr 29, 2022
Alteration B-304.1
Interior renovations (1st floor-residents lounge) per provided plans. (subject to all applicable federal, state and local executive orders.)
Feb 15, 2022
Alteration
Alterations to existing fire alarm system in k-2 cardiology area per plans. subject to field approval and all applicable federal, state, and local executive orders.
Jan 28, 2022
Alter Revision I-2 308.4
Revision to bld2021-01622 per plans. (interior alterations in central pharmacy per plans). subject to field approval and all applicable federal, state, and local executive orders.
Oct 27, 2021
Alteration
Modifications to fire alarm system (1st floor-ct room) per plans. (subject to all applicable federal, state and local executive orders.)
Oct 4, 2021
Alteration
Modifications to fire alarm system (6th fl.-panthogens lab) per plans. (subject to all applicable federal, state and local executive orders.)
Oct 4, 2021
Alteration I-2 308.4
Interior alterations at 6th floor f-6 special pathogens unit per plans. subject to field approval and all applicable federal, state, and local executive orders.
Aug 11, 2021
Alteration
Alterations to existing fire alarm system in central pharmacy per plans. subject to field approval and all applicable federal, state, and local executive orders.
Jul 25, 2021
Alteration I-2 308.4
Interior alterations in central pharmacy per plans. subject to field approval and all applicable federal, state, and local executive orders.
Jun 17, 2021
Alteration I-2 308.4
Alteration of 3rd floor room 7 to install new spec ct equipment per plans. subject to field approval and all applicable federal, state, and local executive orders.
May 17, 2021
Alteration
Interior alterations in scanner room 6 per plans. subject to field approval and all applicable federal, state, and local executive orders.
Apr 19, 2021
Alteration
Install new ct equipment in emergency department ct scan room wc-111 per plans. subject to field approval and all applicable federal, state, and local executive orders.
Apr 19, 2021
Disclaimer: Permit data comes from Detroit's official open data portal. Records may be incomplete for older permits, and not every home-improvement project requires a permit. Verify with the Detroit building department before buying, selling, or planning work.