How to Get a Kitchen Remodel Permit in Miami, FL (2026 Guide)

Everything you need to know about kitchen remodel permits in Miami, FL, local requirements, fees, timelines, and how to apply.

By Joey, Founder · Last updated May 23, 2026 · How we research →

$195 – $780 Permit Fees
about 2 weeks Approval Time
4 Local Rules

Check your specific kitchen remodel project

Get an instant, personalized answer for your exact project details in Miami.

Free Permit Lookup →

Do You Need a Kitchen Remodel Permit in Miami?

Based on Miami's local building codes, you'll need a permit when:

Required·Rule 1

Kitchen renovations involving plumbing changes require permits in Miami, FL.

SourceFlorida Building Code / Miami-Dade County
Required·Rule 2

Kitchen renovations involving wall removal require a building permit in Miami, FL.

SourceFlorida Building Code / Miami-Dade County
Required·Rule 3

Any gas line work in a kitchen requires permits in Miami, FL.

SourceFlorida Building Code / Miami-Dade County

These kitchen remodel projects are typically exempt in Miami:

Exempt·Rule 1

Cosmetic kitchen updates (paint, countertops, cabinet refacing) do not require a permit in Miami, FL.

SourceFlorida Building Code / Miami-Dade County

Permit Fees in Miami

Based on local Miami permit data, fees for kitchen remodel projects typically range:

$195 – $780 Miami Permit Fee Range

Here's how fees break down by project scope nationally:

Project ScopeTypical Permit Fee
Cosmetic remodel (no plumbing/electrical/structural)Usually exempt
Electrical permit (adding circuits or outlets)$50 – $500
Plumbing permit (moving or adding fixtures)$50 – $500
Building permit (structural changes)$150 – $900
Full gut remodel (all trade permits combined)$500 – $3,000+
Structural engineering (wall removal, if needed)$1,000 – $1,800 (separate from permit)

Fees are typically calculated based on estimated project value. Contact Building Department for exact amounts.

How Long Does It Take?

In Miami, typical approval time for kitchen remodel permits is about 2 weeks.

More complex projects requiring structural review or variances may take longer. Simple projects may qualify for expedited or over-the-counter review in some cases.

How to Apply for a Kitchen Remodel Permit in Miami

  1. 1 Check requirements: Use our free lookup tool or contact Building Department to confirm your project needs a permit.
  2. 2 Gather documents: Prepare your application, site plan, construction drawings, and any other required documents.
  3. 3 Submit online: Miami accepts applications online at Building Department.
  4. 4 Pay fees: Pay the applicable permit fees ($195 – $780).
  5. 5 Wait for approval: Your application will be reviewed by Miami plan reviewers. Typical turnaround is about 2 weeks.
  6. 6 Begin work: Once approved, post your permit visibly at the job site before starting work.
  7. 7 Schedule inspections: Call Building Department at (305) 416-1100 to schedule required inspections at each phase of the project.

Miami Building Department Contact

NameBuilding Department
Apply OnlineApply online
Address444 SW 2nd Ave, 2nd Floor, Miami, FL 33130
HoursMon-Fri 8am-4:30pm

Required Inspections in Miami

Most kitchen remodel projects in Miami require inspections at each construction stage:

Inspection·Stage 1

Rough Framing Inspection, Correct lumber sizes, spacing, and species/grade per approved plans, headers and beams matching engineering calculations, proper bearing and connections, metal connectors and joist hangers installed with correct fasteners, fireblocking in place, and overall structural integrity.

WhenAfter wall removal, new framing, and structural modifications are complete but before insulation or drywall, inspector must see all structural work
Common FailuresBeam or header undersized for the span, missing or incorrect metal connectors, improper bearing at beam ends, fireblocking not installed.
Inspection·Stage 2

Rough Electrical Inspection, Wire gauge appropriate for circuit amperage, proper box placement and fill calculations, two dedicated 20-amp small-appliance circuits present (NEC 210.11(C)(1)), GFCI and AFCI protection where required, dedicated circuits for dishwasher and disposal, and countertop receptacle spacing compliance.

WhenAfter wiring is run but before walls are closed, often inspected at the same time as framing
Common FailuresMissing dedicated 20-amp kitchen circuits, incorrect wire gauge, GFCI not provided for all kitchen receptacles, countertop outlets spaced too far apart.
Inspection·Stage 3

Rough Plumbing and Gas Inspection, Supply lines properly sized and supported, drain system properly sloped and vented, gas piping pressure-tested (typically 15 PSI air test held for 15+ minutes with no pressure drop), no leaks at any joints, and proper pipe materials and connections.

WhenAfter supply lines, drain/waste/vent piping, and gas lines are installed but before walls are closed
Common FailuresGas piping failing pressure test, drain slope insufficient, vent too far from trap, undersized supply lines for new fixture locations.
Inspection·Stage 4

Final Inspection, All outlets work and GFCI trips properly, all covers on electrical boxes, plumbing has no leaks and drains properly, gas appliances connected and leak-tested, structural connections complete, range hood exhausts to exterior, smoke and CO detectors installed and functional, and overall compliance with approved plans.

WhenAfter all work is complete, cabinets, countertops, appliances, and fixtures installed and connected
Common FailuresGFCI not functioning on all kitchen receptacles, gas leak at appliance connection, range hood not vented to exterior, uncovered electrical boxes.

Schedule inspections with Building Department at (305) 416-1100 at least 24–48 hours in advance.

Frequently Asked Questions

Whether you need a permit depends on the size and scope of your kitchen remodel project. In Miami, some smaller projects are exempt while larger ones require a permit. Use our free lookup tool to check your specific situation.

Permit fees for kitchen remodel projects in Miami typically range from $195 – $780. Fees are usually based on the estimated project value.

Typical approval time in Miami is about 2 weeks. Complex projects requiring structural review may take longer.

In most cases, homeowners in Miami can pull permits and perform work on their own primary residence as an owner-builder. You're still responsible for meeting all code requirements and passing inspections.

Working without a required permit in Miami can result in fines, stop-work orders, required removal of completed work, and complications when selling your home.

Ready to check your kitchen remodel project in Miami?

Use our free lookup tool to get a personalized answer based on your specific project details.

Free Permit Lookup →

Kitchen Remodel Permits in Nearby Cities

See kitchen remodel permit requirements in other Florida cities:

See Detailed Kitchen Remodel Rules for Miami

View all local rules, exemptions, and fee details on the permit page.

Kitchen Remodel Permit Rules →
Disclaimer: This guide provides general information about kitchen remodel permit requirements in Miami, FL. Requirements can change. Always confirm with Building Department before starting any project. PermitMint provides general guidance, not legal advice.