Driveway Permit Requirements in Pembroke Pines, FL

Pembroke Pines is a city of 171,178 residents in Florida that follows the 2021 IRC. Pembroke Pines is generally more lenient than the standard IRC when it comes to driveway projects, more exemptions and fewer permit triggers. You're looking at roughly $150 – $500 in permit fees, plan on about 3 weeks for approval, plus you can apply online.

By Joey, Founder · Last verified March 29, 2026 · How we research →

Population: 171,178 Code: 2021 Verified: 2026-03-29 4 local rules

When you don’t need a Driveway permit in Pembroke Pines

Exempt·Rule 1

Replacing an existing driveway in the same footprint with no changes to the curb cut is generally exempt from permit requirements.

SourceFlorida Building Code / 2021 IRC with local amendments

When you need a Driveway permit in Pembroke Pines

Required·Rule 1

Any new curb cut requires an encroachment or right-of-way permit. This involves work in the public right-of-way and must meet ADA sidewalk crossing requirements. Contact your city's public works department.

Estimated Fee$150 – $500
Typical Timelineabout 3 weeks
SourceFlorida Building Code / 2021 IRC with local amendments
Required·Rule 2

New driveways require a permit. If a new curb cut is needed, an encroachment or right-of-way permit is also required for work in the public right-of-way. The driveway must meet width limits and impervious surface requirements.

Estimated Fee$100 – $400
Typical Timelineabout 2 weeks
SourceFlorida Building Code / 2021 IRC with local amendments
Required·Rule 3

Widening or extending an existing driveway typically requires a permit because it increases impervious surface coverage and may affect drainage. If the widening involves a modified curb cut, a right-of-way permit is also required.

Estimated Fee$75 – $300
Typical Timelineabout 2 weeks
SourceFlorida Building Code / 2021 IRC with local amendments

What Makes Pembroke Pines Different

Here's how Pembroke Pines's driveway rules stack up against the standard IRC baseline that most of the country follows.

Stricter Than the IRC

Any new curb cut requires an encroachment or right-of-way permit. This involves work in the public right-of-way and must meet ADA sidewalk crossing requirements. Contact your city's public works department.

New driveways require a permit. If a new curb cut is needed, an encroachment or right-of-way permit is also required for work in the public right-of-way. The driveway must meet width limits and impervious surface requirements.

Widening or extending an existing driveway typically requires a permit because it increases impervious surface coverage and may affect drainage. If the widening involves a modified curb cut, a right-of-way permit is also required.

1 rule match the IRC baseline, no surprises there.

Driveway Permit Costs: Pembroke Pines vs. Nearby

Pembroke Pines comes in on the low side for Florida. You're looking at $75 – $500 here, compared to the state average of $108 – $397.

CityEstimated Fee
Pembroke Pines $75 – $500
Jacksonville $75 – $500
Miami $75 – $500
Tampa $75 – $500

Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Pembroke Pines permit costs →

Zoning & HOA Considerations

Zoning

Driveways that require a new curb cut involve public right-of-way work and always need a permit. Driveway width and impervious surface limits vary by city.

HOA Communities

If you live in an HOA community: hOAs often regulate driveway materials, width, and appearance. Widening a driveway or changing from concrete to gravel (or vice versa) may need architectural review approval.

Estimated Project Timeline in Pembroke Pines

Here's a typical timeline for a driveway project in Pembroke Pines, FL:

Week 1
Get quotes & finalize design
Contact licensed contractors, get 3+ quotes, finalize project scope and drawings (plan drawings required).
Week 2
Prepare permit documents
Contractor prepares site plan, construction drawings, and permit application. Gather required documents per your city's checklist.
Week 3
Submit permit application
Your contractor submits the application to Pembroke Pines's building department, apply online here.
Week 4-6
Plan review & approval
Typical processing time in Pembroke Pines: about 3 weeks. Plan review examiner checks drawings for code compliance.
Week 7+
Construction & inspections
Post the permit card on site. Work begins. Schedule inspections at required stages (varies by project). Final inspection required before closing the permit.

Timeline is based on Pembroke Pines's typical about 3 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.

Need a Driveway permit in Pembroke Pines, FL?

Answer a few quick questions for a personalized answer about your specific project.

Check Now, Free →

Building Department Contact

NameBuilding Department
Address601 City Center Way, 2nd Floor, Pembroke Pines, FL 33025
HoursMon-Thu 7:30am-5pm

Frequently Asked Questions

Estimated permit fees for Driveway projects in Pembroke Pines, FL range from $75 – $500. Fees vary based on project scope and valuation.

It depends on the specifics of your project. Some smaller Driveway projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.

Working without a required permit in Pembroke Pines can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.

Typical approval time for Driveway permits in Pembroke Pines is about 3 weeks. More complex projects may take longer if plan review is required.

If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.

Learn More About Driveway Permits

Read our complete guide covering permit requirements, costs, common exemptions, and the application process.

Read Driveway Guide →

Estimate your permit fees →

Disclaimer: This information was last verified on 2026-03-29. Building permit requirements may change. Zoning requirements (setbacks, lot coverage, height limits) are separate and vary by location. Always confirm with your local building and planning departments before starting your project. PermitMint provides general guidance, not legal advice.