Demolition Permit Requirements in Pembroke Pines, FL
Pembroke Pines is a city of 171,178 residents in Florida that follows the 2021 IRC. Pembroke Pines is generally more lenient than the standard IRC when it comes to demolition projects, more exemptions and fewer permit triggers. You're looking at roughly $200 – $1,000 in permit fees, plan on about 3 weeks for approval, plus you can apply online.
By Joey, Founder · Last verified March 29, 2026 · How we research →
When you don’t need a Demolition permit in Pembroke Pines
Removing a small accessory structure (shed, carport, small outbuilding) built after 1978 and not in a historic district may be exempt from a demolition permit. However, utility disconnection and proper disposal are still required. Check with your building department.
When you need a Demolition permit in Pembroke Pines
Full building demolition requires a demolition permit. All utilities (gas, electric, water, sewer) must be disconnected before work begins. An asbestos survey is required for structures built before 1978.
Demolition of structures built before 1978 requires a permit and an asbestos survey before any work begins. Federal EPA NESHAP regulations require asbestos-containing materials to be identified and properly abated. Lead paint may also be present and require special handling.
Partial demolition that involves removing structural elements (walls, roof sections, floors) requires a building permit. Structural plans may be required showing how the remaining structure will be supported.
What Makes Pembroke Pines Different
Here's how Pembroke Pines's demolition rules stack up against the standard IRC baseline that most of the country follows.
More Lenient Than the IRC
Removing a small accessory structure (shed, carport, small outbuilding) built after 1978 and not in a historic district may be exempt from a demolition permit. However, utility disconnection and proper disposal are still required. Check with your building department.
3 rules match the IRC baseline, no surprises there.
Demolition Permit Costs: Pembroke Pines vs. Nearby
Pembroke Pines comes in on the low side for Florida. You're looking at $100 – $1,000 here, compared to the state average of $166 – $757.
| City | Estimated Fee |
|---|---|
| Pembroke Pines | $100 – $1,000 |
| Jacksonville | $100 – $1,000 |
| Miami | $100 – $1,000 |
| Tampa | $100 – $1,000 |
Fees shown are estimates based on local building code data. Actual fees may vary based on project scope and valuation. See all Pembroke Pines permit costs →
Zoning & HOA Considerations
Properties in historic districts may require historic review board approval before demolition. Some cities require a waiting period for demolition permits to allow for public comment.
If you live in an HOA community: demolition of visible structures (garages, sheds, accessory buildings) may require HOA notification or approval. Check your CC&Rs, some communities require maintaining certain structures or replacing them within a set timeframe.
Estimated Project Timeline in Pembroke Pines
Here's a typical timeline for a demolition project in Pembroke Pines, FL:
Timeline is based on Pembroke Pines's typical about 3 weeks permit processing time. Actual timelines vary by project complexity, completeness of application, and current department workload.
Need a Demolition permit in Pembroke Pines, FL?
Answer a few quick questions for a personalized answer about your specific project.
Check Now, Free →Building Department Contact
Frequently Asked Questions
Estimated permit fees for Demolition projects in Pembroke Pines, FL range from $100 – $1,000. Fees vary based on project scope and valuation.
It depends on the specifics of your project. Some smaller Demolition projects may be exempt from permit requirements, while larger ones typically require a permit. Use our free lookup tool to check your specific situation.
Working without a required permit in Pembroke Pines can result in fines, stop-work orders, being required to remove completed work, and complications when selling your home. It's always best to check first.
Typical approval time for Demolition permits in Pembroke Pines is about 3 weeks. More complex projects may take longer if plan review is required.
If you live in an HOA community, you may need architectural review approval in addition to a building permit. HOA rules and city building codes are separate, you may need to satisfy both. Review your CC&Rs and submit to your HOA's architectural review committee before starting work.
Learn More About Demolition Permits